3620 1/2 S GRAMERCY PL 90018
Certificate Information: 3620 1/2 S GRAMERCY PL 90018
- Application / Permit
- 24016-30000-10462
- Plan Check / Job No.
- B24WL00663
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage to ADU per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/5/2024
- Issuing Office
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2024 | JASON JANGADA |
| Corrections Issued | 4/5/2024 | JASON JANGADA |
| Applicant returned to address corrections | 8/21/2024 | YASHAR EMAMI |
| Plan Check Approved | 9/4/2024 | JOHNPAUL ISIP |
| Issued | 9/5/2024 | APPLICANT |
| CofO in Progress | 2/3/2025 | SABAS ALONSO |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
| CofO Issued | 2/11/2025 | DEROLD HAUFF |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 4/12/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2024 | TREVOR QUAN |
| Construction near power lines | Cleared | 8/15/2024 | RIDWAN HARDY |
Contact Information
| Contractor | California Designers Remodeling Inc; Lic. No.: 946160-B | 22567 MARGARITA DRIVE WOODLAND HILLS, CA 91364 |
| Engineer | Alferez,, Vicente Narvaez; Lic. No.: C53875 | 460 E CARSON PLAZA DR STE 212 CARSON, CA 90746 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/13/2024 | Partial Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 9/24/2024 | Partial Approval | SABAS ALONSO |
| Sewer | 9/24/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 9/24/2024 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/15/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 10/15/2024 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 10/15/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 10/15/2024 | Approved | SABAS ALONSO |
| METHANE-Rough | 10/15/2024 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 10/23/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 10/28/2024 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 10/28/2024 | Approved | SABAS ALONSO |
| Deputy Drilled-In Anchors | 10/30/2024 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/1/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 11/1/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 11/1/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2024 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 11/4/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 11/8/2024 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 11/8/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 11/8/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 11/8/2024 | Partial Approval | SABAS ALONSO |
| Insulation | 11/14/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 11/21/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/6/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/17/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 1/17/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 1/17/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 1/17/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 1/17/2025 | Approved | SABAS ALONSO |
| HVAC-Final | 1/17/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 1/17/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 1/17/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 1/23/2025 | Approved | SABAS ALONSO |
| Final | 1/23/2025 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 1/23/2025 | Approved | SABAS ALONSO |
| PLUMBING-Final | 1/23/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Approved | SABAS ALONSO |
| Final | 1/28/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 1/31/2025 | Approved | SABAS ALONSO |
| Final | 1/31/2025 | OK to Issue CofO | SABAS ALONSO |
| HVAC-Final | 1/31/2025 | Approved | SABAS ALONSO |
| PLUMBING-Final | 1/31/2025 | Approved | SABAS ALONSO |