1162 S DANIELS DR 90035

Certificate Information: 1162 S DANIELS DR 90035

Application / Permit
24016-30000-09764
Plan Check / Job No.
B24WL00614
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Additions and interior and exterior alteration of (E) SFD, remove (E) entry porch roof and replace with a larger california framing roof.
Permit Issued
Issued on 4/5/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2024 APPLICANT
Assigned to Plan Check Engineer 3/23/2024 EDWIN ESPIN
Corrections Issued 3/24/2024 EDWIN ESPIN
Building Plans Picked Up 3/28/2024 APPLICANT
Applicant returned to address corrections 4/4/2024 JAHANSHAH POURHASSAN
Plan Check Approved 4/5/2024 JAHANSHAH POURHASSAN
Issued 4/5/2024 APPLICANT
CofO in Progress 9/10/2024 ARAM AVEDISIAN
Permit Finaled 9/17/2024 RICHARD STEINBACH
Permit Finaled 9/17/2024 RICHARD STEINBACH
CofO Issued 9/17/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/5/2024 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 4/5/2024 HISASHI KOBAYAKAWA

Contact Information

Architect , ; Lic. No.: C34486       ,
Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/14/2024 Approved MEL KHACHATOURIAN
ELECTRICAL-Rough 5/21/2024 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 5/23/2024 Approved ASHLEY THOMPSON
Green Building Rough 5/23/2024 Approved ASHLEY THOMPSON
HVAC-Rough 5/23/2024 Approved ASHLEY THOMPSON
METHANE-Rough 5/23/2024 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Approved KIRK SANDERS
Shower Pan 6/4/2024 Approved KIRK SANDERS
Insulation 6/28/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 6/28/2024 Approved SEAN HAUPT
Drywall Nailing 7/2/2024 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 7/2/2024 Approved ASHLEY THOMPSON
ELECTRICAL-Final 8/30/2024 Approved ARAM AVEDISIAN
Final 8/30/2024 Corrections Issued ARAM AVEDISIAN
Green Building Final 8/30/2024 Approved ARAM AVEDISIAN
HVAC-Final 8/30/2024 Approved ARAM AVEDISIAN
PLUMBING-Final 8/30/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 8/30/2024 Approved ARAM AVEDISIAN
Final 9/10/2024 OK to Issue CofO ARAM AVEDISIAN
Footing/Foundation/Slab 9/10/2024 Approved ARAM AVEDISIAN