6631 W COLGATE AVE 90048
Certificate Information: 6631 W COLGATE AVE 90048
- Application / Permit
- 24016-30000-08816
- Plan Check / Job No.
- B24WL00558
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage and rec-room into an ADU per CA Govt. Code 65852.2(e)(1)(A). Existing pergola to be removed. Design per WFPP.
- Permit Issued
- Issued on 8/23/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2024 | RICHARD GARCIA |
| Corrections Issued | 3/15/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 3/18/2024 | APPLICANT |
| Applicant returned to address corrections | 7/24/2024 | YASHAR EMAMI |
| Plan Check Approved | 8/21/2024 | CAROLEAN BASMA |
| Issued | 8/23/2024 | APPLICANT |
| CofO in Progress | 6/3/2025 | MICHAEL PELHAM |
| Permit Finaled | 6/3/2025 | RICHARD STEINBACH |
| CofO Issued | 6/3/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/3/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 7/18/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2024 | JUSTIN BICOL |
| ZI | Cleared | 7/22/2024 | ROSALINDA MEZA |
| Construction near power lines | Cleared | 8/14/2024 | RIDWAN HARDY |
Contact Information
| Architect | Rigo, De Righi, Fabio N; Lic. No.: C27735 | 226 S BEVERLY DRIVE #220 BEVERLY HILLS, CA 90212 |
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 9/12/2024 | Partial Approval | ARAM AVEDISIAN |
| Pre-Inspection | 9/12/2024 | Corrections Issued | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 9/12/2024 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/15/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Final | 11/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 11/15/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 11/15/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Final | 11/15/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 11/15/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 11/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 12/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/9/2025 | Approved | EVAN COOPER |
| Final | 5/9/2025 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/9/2025 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 5/9/2025 | Approved | EVAN COOPER |
| Service/Power Release | 5/20/2025 | Approved | EVAN COOPER |
| Final | 6/3/2025 | OK to Issue CofO | MICHAEL PELHAM |