3650 S CENTINELA AVE 90066

Certificate Information: 3650 S CENTINELA AVE 90066

Application / Permit
24016-30000-06870
Plan Check / Job No.
X24WL01339
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over existing solid sheathing (_2)__Squares. Class A roof covering is required within a Very High Fire Hazard Severity Zone (VHFHSZ). For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council (CRRC). Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141.0(b) 2B. 6. Installation of security bars for dwellings/apartments. Quick release required in bedrooms per California Building Code Part 12, Chapter 12-3. 26. Concrete block freestanding masonry fence walls constructed per Information Bulletin P/BC 2020-096 located in residential zones, maximum 6 feet height above grade, and not located in the required front yard or within 5 feet of the side street lot line of a reverse corner lot (subject to additional limitations of LAMC Section 12.22C20(f) and Information bulletin P/ZC 2002-002). Repair of water, dry-rot stairs in residential buildings (less than 10% of replacement cost of stairs). Replacement of damaged framing members (less than 10% of replacement cost of building) for houses and duplexes (not including decks).
Permit Issued
Issued on 2/29/2024
Issuing Office
West Los Angeles
Current Status
Issued on 2/29/2024

Permit Application Status History

Issued 2/29/2024 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 12/2/2024 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 12/2/2024 Not Ready for Inspection FARHAD DADBIN