6101 W 83RD PL 90045

Certificate Information: 6101 W 83RD PL 90045

Application / Permit
24016-30000-06845
Plan Check / Job No.
B24WL00468
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Trellised roof patio cover (9' x 25') addition to rear side of (e) 2-story SFD and remodel the house
Permit Issued
Issued on 1/30/2025
Issuing Office
West Los Angeles
Current Status
Issued on 1/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/29/2024 APPLICANT
Assigned to Plan Check Engineer 3/7/2024 REZA HAGHIGHAT
Corrections Issued 3/15/2024 REZA HAGHIGHAT
Quality Review Completed 3/26/2024 CHIHARU SUZUKI
Building Plans Picked Up 4/2/2024 APPLICANT
Plan Check Approved 1/30/2025 REZA HAGHIGHAT
Issued 1/30/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/11/2024 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 4/11/2024 HISASHI KOBAYAKAWA

Contact Information

Contractor Ludwig S C Construction Llc; Lic. No.: 991853-B 3969 ALLA RD      LOS ANGELES, CA 90066
Engineer Galbreath,, Sean; Lic. No.: S5653 600 SOUTH LAKE AVE STE 308      PASADENA, CA 91106

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Interior/Exterior Lathing 3/25/2025 Partial Approval JESUS PINEDA
ELECTRICAL-Rough 3/26/2025 Approved JESUS PINEDA
HVAC-Rough 3/26/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 3/26/2025 Corrections Issued JESUS PINEDA
Shower Pan 3/28/2025 Approved JAYLIN GRAVITTE
BUILDING-Rough-Frame 4/1/2025 Partial Approval JESUS PINEDA
HVAC-Rough 4/1/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 4/1/2025 Approved JESUS PINEDA
PLUMBING-Rough 4/1/2025 Approved JESUS PINEDA
Insulation 4/3/2025 Approved JESUS PINEDA
Drywall Nailing 4/9/2025 Approved BOBBY KEY
Special/Order Compliance 4/9/2025 Partial Inspection JAYLIN GRAVITTE
BUILDING-Rough-Frame 6/23/2025 Partial Approval ARAM AVEDISIAN
Final 6/23/2025 Partial Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 6/23/2025 Partial Approval ARAM AVEDISIAN
Green Building Final 6/23/2025 Partial Approval ARAM AVEDISIAN
Green Building Rough 6/23/2025 Partial Approval ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/23/2025 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 6/23/2025 Approved ARAM AVEDISIAN