6101 W 83RD PL 90045
Certificate Information: 6101 W 83RD PL 90045
- Application / Permit
- 24016-30000-06845
- Plan Check / Job No.
- B24WL00468
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Trellised roof patio cover (9' x 25') addition to rear side of (e) 2-story SFD and remodel the house
- Permit Issued
- Issued on 1/30/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2024 | REZA HAGHIGHAT |
| Corrections Issued | 3/15/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 3/26/2024 | CHIHARU SUZUKI |
| Building Plans Picked Up | 4/2/2024 | APPLICANT |
| Plan Check Approved | 1/30/2025 | REZA HAGHIGHAT |
| Issued | 1/30/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2024 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 4/11/2024 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Ludwig S C Construction Llc; Lic. No.: 991853-B | 3969 ALLA RD LOS ANGELES, CA 90066 |
| Engineer | Galbreath,, Sean; Lic. No.: S5653 | 600 SOUTH LAKE AVE STE 308 PASADENA, CA 91106 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 3/25/2025 | Partial Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 3/26/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 3/26/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 3/26/2025 | Corrections Issued | JESUS PINEDA |
| Shower Pan | 3/28/2025 | Approved | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 4/1/2025 | Partial Approval | JESUS PINEDA |
| HVAC-Rough | 4/1/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 4/1/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 4/1/2025 | Approved | JESUS PINEDA |
| Insulation | 4/3/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 4/9/2025 | Approved | BOBBY KEY |
| Special/Order Compliance | 4/9/2025 | Partial Inspection | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 6/23/2025 | Partial Approval | ARAM AVEDISIAN |
| Final | 6/23/2025 | Partial Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 6/23/2025 | Partial Approval | ARAM AVEDISIAN |
| Green Building Final | 6/23/2025 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 6/23/2025 | Partial Approval | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2025 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 6/23/2025 | Approved | ARAM AVEDISIAN |