2701-2703 S GREENFIELD AVE 90064

Certificate Information: 2701-2703 S GREENFIELD AVE 90064

Application / Permit
24016-30000-05204
Plan Check / Job No.
B24WL00365
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO (N) JADU PER CA GOVT. CODE 65852.2 (E)(1)(A) AND 65852.2
Permit Issued
Issued on 9/5/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2024 APPLICANT
Assigned to Plan Check Engineer 2/17/2024 AMY GUEVARRA
Corrections Issued 2/23/2024 AMY GUEVARRA
Building Plans Picked Up 2/23/2024 APPLICANT
Plan Check Approved 9/3/2024 NEHEMIAS RAMOS
Issued 9/5/2024 APPLICANT
CofO in Progress 12/26/2024 DANIEL VERA
CofO Issued 12/28/2024 RICHARD STEINBACH
Permit Finaled 12/28/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/8/2024 ANDREA SAINT-ANTONIN
Sewer availability Cleared 6/8/2024 ANDREA SAINT-ANTONIN
Eng Process Fee Ord 176,300 Cleared 6/10/2024 ANDREA SAINT-ANTONIN
Grading Pre-Inspection Cleared 7/12/2024 ALEXANDER HELFER
Specific Plan Cleared 8/26/2024 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/16/2024 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/16/2024 Corrections Issued DANIEL VERA
BUILDING-Rough-Frame 10/15/2024 Partial Approval MICHAEL ALLEN
Green Building Rough 10/15/2024 Partial Inspection MICHAEL ALLEN
ELECTRICAL-Rough 10/22/2024 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Approved DANIEL VERA
PLUMBING-Rough 10/22/2024 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Not Ready for Inspection DANIEL VERA
Gas Test 10/24/2024 Approved DANIEL VERA
Insulation 10/24/2024 Corrections Issued DANIEL VERA
PLUMBING-Rough 10/24/2024 Approved DANIEL VERA
PLUMBING-Rough 10/25/2024 Approved DANIEL VERA
Insulation 10/30/2024 Not Ready for Inspection REGINA MENDEZ
BUILDING-Rough-Frame 10/31/2024 Approved DANIEL VERA
Green Building Rough 10/31/2024 Approved DANIEL VERA
Insulation 10/31/2024 Approved DANIEL VERA
Interior/Exterior Lathing 10/31/2024 Partial Approval DANIEL VERA
Drywall Nailing 11/13/2024 Approved REGINA MENDEZ
Interior/Exterior Lathing 11/26/2024 Approved REGINA MENDEZ
ELECTRICAL-Final 12/19/2024 Approved BOBBY KEY
Final 12/19/2024 Corrections Issued BOBBY KEY
Green Building Final 12/19/2024 Approved BOBBY KEY
HVAC-Final 12/19/2024 Corrections Issued BOBBY KEY
MERV13>=Final 12/19/2024 Approved BOBBY KEY
PLUMBING-Final 12/19/2024 Partial Approval BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/19/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 12/19/2024 Approved BOBBY KEY
Special/Order Compliance 12/19/2024 Partial Inspection JAYLIN GRAVITTE
Final 12/23/2024 OK to Issue CofO DANIEL VERA