962-964 N LUCILE AVE 90026

Certificate Information: 962-964 N LUCILE AVE 90026

Application / Permit
24016-30000-04054
Plan Check / Job No.
B24WL00311
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Remodel (E) Duplex per engineering design. "COMPLY WITH DEPARTMENT ORDER effective date 04/30/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". *** SEE COMMENTS***
Permit Issued
Issued on 3/19/2024
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 3/2/2026

Permit Application Status History

Submitted 2/8/2024 APPLICANT
Assigned to Plan Check Engineer 2/14/2024 RICHARD GARCIA
Corrections Issued 2/14/2024 RICHARD GARCIA
Building Plans Picked Up 2/16/2024 APPLICANT
Applicant returned to address corrections 3/5/2024 ALFREDO JARA
Plan Check Approved 3/6/2024 ZENA HADDIS
Issued 3/19/2024 APPLICANT
Permit Finaled 3/2/2026 ROBERT NILES

Permit Application Clearance Information

Tenant Habitability Plan Cleared 2/29/2024 RICARDO BOHORQUEZ

Contact Information

Contractor Brick & Hammer; Lic. No.: 951717-B 4525 KINGSWELL AVE      LOS ANGELES, CA 90027
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/20/2024 Partial Inspection FREDDIE RIVERA
Pre-Inspection 3/27/2024 Corrections Issued COREY HUPP
Footing/Foundation/Slab 5/10/2024 Approved COREY HUPP
BUILDING-Rough-Frame 8/15/2024 Partial Approval COREY HUPP
Rough-Elec/Plmb/HVAC 8/15/2024 Partial Approval COREY HUPP
BUILDING-Rough-Frame 8/20/2024 Approved COREY HUPP
HVAC-Rough 8/20/2024 Not Ready for Inspection COREY HUPP
Interior/Exterior Lathing 8/27/2024 Approved EMIL OPFFER
Insulation 9/4/2024 Approved EMIL OPFFER
Drywall Nailing 9/11/2024 Approved EMIL OPFFER
ELECTRICAL-Rough 4/15/2025 Approved EMIL OPFFER
Special/Order Compliance 4/15/2025 Not Ready for Inspection EMIL OPFFER
Underground Mechanical 4/15/2025 Not Ready for Inspection EMIL OPFFER
ELECTRICAL-Final 12/23/2025 Corrections Issued ROBERT NILES
PLUMBING-Final 12/23/2025 Approved ROBERT NILES
ELECTRICAL-Final 12/29/2025 Approved JOEL ORDAZ
Final 12/29/2025 Not Ready for Inspection JOEL ORDAZ
HVAC-Final 12/29/2025 Approved JOEL ORDAZ
SGSOV-Seismic Gas S/O Valve 12/29/2025 SGSOV Not Ready JOEL ORDAZ
Smoke Detectors 12/29/2025 Approved JOEL ORDAZ
Order to Comply 12/31/2025 OTC Issued JOEL ORDAZ
Final 2/3/2026 Conditional Approval ROBERT NILES
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Approved ROBERT NILES
Final 3/2/2026 Permit Finaled ROBERT NILES