1431 N STRADELLA ROAD 90077
Certificate Information: 1431 N STRADELLA ROAD 90077
- Application / Permit
- 24016-30000-03698
- Plan Check / Job No.
- B24WL00286
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Structural Alteration and Addition To (E) SFD with Attached 3-Car Garage. Scope of Work To Include: Lower Height of (E) Covered Front Porch; Remove and Replace Roof of (E ) Attached Garage for a Roof Deck and (N) 10'x20' Open Attached Lattice Roof On The Side of SFD.
- Permit Issued
- Issued on 4/1/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2024 | EDWIN ESPIN |
| Corrections Issued | 2/11/2024 | EDWIN ESPIN |
| Building Plans Picked Up | 2/12/2024 | APPLICANT |
| Plan Check Approved | 3/14/2024 | JAHANSHAH POURHASSAN |
| Issued | 4/1/2024 | APPLICANT |
| CofO in Progress | 5/12/2026 | CARLOS MATAMOROS |
| Permit Finaled | 5/12/2026 | RICHARD STEINBACH |
| CofO Issued | 5/12/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/12/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2024 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 2/28/2024 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 3/12/2024 | VASIL MIHALEV |
Contact Information
| Architect | , ; Lic. No.: C34881 | , |
| Contractor | My General Construction Inc; Lic. No.: 1029958-B | 160 N LURING, SUITE C PALM SPRINGS, CA 92262 |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 3876 HUNTERS GROVE CT MOORPARK, CA 93021 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/11/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 4/11/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 4/11/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 4/11/2024 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 4/11/2024 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 8/9/2024 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 8/9/2024 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 8/12/2024 | Corrections Issued | MICHAEL PELHAM |
| Footing/Foundation/Slab | 10/11/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Special/Order Compliance | 10/11/2024 | Partial Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 10/25/2024 | Partial Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/8/2024 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 11/8/2024 | Corrections Issued | MICHAEL PELHAM |
| Footing/Foundation/Slab | 12/12/2024 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 12/12/2024 | Partial Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/27/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 12/27/2024 | Not Ready for Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 12/30/2024 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 2/6/2025 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 2/6/2025 | Partial Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 3/11/2025 | Partial Inspection | MICHAEL PELHAM |
| Structural Steel Frame | 3/11/2025 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/14/2025 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 3/14/2025 | Approved | CHRISTOPHER WILSON |
| Special/Order Compliance | 3/14/2025 | Partial Inspection | STEPHANIE SWANSON |
| Special/Order Compliance | 3/25/2025 | Partial Inspection | MICHAEL PELHAM |
| Wood Frame | 3/25/2025 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 3/27/2025 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 3/27/2025 | Partial Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 3/27/2025 | Partial Inspection | MICHAEL PELHAM |
| Pre-Inspection | 12/11/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 5/8/2026 | Approved | CARLOS MATAMOROS |
| Final | 5/8/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/8/2026 | Approved | CARLOS MATAMOROS |
| Green Building Final | 5/8/2026 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 5/8/2026 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 5/8/2026 | Approved | CARLOS MATAMOROS |
| Final | 5/12/2026 | OK to Issue CofO | CARLOS MATAMOROS |