2000 S COTNER AVE 90025

Certificate Information: 2000 S COTNER AVE 90025

Application / Permit
24016-30000-02400
Plan Check / Job No.
B24WL00198
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Gymnasium
Work Description
Core and shell only permit for change of use from Barbershop/Salon to Gym and Spa (4,917 sf). See comments.
Permit Issued
Issued on 12/3/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2024 APPLICANT
Assigned to Plan Check Engineer 2/1/2024 REZA HAGHIGHAT
Assigned to Zoning Architect 2/1/2024 REZA HAGHIGHAT
Corrections Issued 2/3/2024 REZA HAGHIGHAT
Disabled Access Plans Picked Up 2/12/2024 APPLICANT
Quality Review Completed 2/20/2024 KAVIAN REFAHI
Building Plans Picked Up 2/22/2024 APPLICANT
Applicant returned to address corrections 3/27/2024 REZA HAGHIGHAT
Plan Check Approved 12/3/2024 REZA HAGHIGHAT
Issued 12/3/2024 APPLICANT
CofO in Progress 8/7/2025 RICARDO ROBLES
Permit Finaled 8/7/2025 DAVID TSAU
CofO Issued 8/7/2025 DAVID TSAU
Permit Finaled 8/7/2025 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 3/27/2024 BRENDEN HAWK
ZA Case Cleared 3/27/2024 YINGSHI HUANG
Eng Process Fee Ord 176,300 Cleared 4/1/2024 BRENDEN HAWK
Sewer availability Cleared 4/1/2024 BRENDEN HAWK
DAS Clearance Cleared 4/30/2024 REZA HAGHIGHAT
Specific Plan Cleared 6/26/2024 JOSHUA JONES
Fire Marshal Fire Life Safety Cleared 11/12/2024 FIRE DEPARTMENT
Zoning Plan Check Cleared 12/3/2024 REZA HAGHIGHAT

Contact Information

Architect , ; Lic. No.: C33846 2917 W TEMPLE ST #101   LOS ANGELES    , CA 90026
Contractor Owner-Builder       ,

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 2/14/2025 Partial Inspection GRANT WOODS
METHANE-Final 2/14/2025 Not Ready for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 2/14/2025 SGSOV Not Ready GRANT WOODS
Smoke Detectors 2/14/2025 Not Ready for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 3/4/2025 SGSOV Not Ready AMANUEL BERHE
Special/Order Compliance 3/5/2025 Conditional Approval GRANT WOODS
Final 7/15/2025 OK to Issue CofO RICARDO ROBLES
METHANE-Final 7/15/2025 Approved RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV Approved RICARDO ROBLES
Smoke Detectors 7/15/2025 Approved RICARDO ROBLES