2105 S CAMDEN AVE 90025

Certificate Information: 2105 S CAMDEN AVE 90025

Application / Permit
24016-30000-01461
Plan Check / Job No.
B24WL00126
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Converting existing detached garage to an ADU per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/15/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2024 APPLICANT
Assigned to Plan Check Engineer 1/20/2024 JASON JANGADA
Corrections Issued 1/20/2024 JASON JANGADA
Building Plans Picked Up 1/22/2024 APPLICANT
Applicant returned to address corrections 2/14/2024 AMY GUEVARRA
Applicant returned to address corrections 3/1/2024 JAHANSHAH POURHASSAN
Plan Check Approved 3/15/2024 JAHANSHAH POURHASSAN
Issued 3/15/2024 APPLICANT
CofO in Progress 3/13/2025 KIRK SANDERS
CofO Issued 3/25/2025 RICHARD STEINBACH
Permit Finaled 3/25/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/22/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 1/22/2024 DARIN LAM
Sewer availability Cleared 1/22/2024 DARIN LAM
Construction near power lines Cleared 2/14/2024 OSCAR CASTRO
Specific Plan Cleared 2/23/2024 JOSHUA JONES
Grading Pre-Inspection Cleared 3/2/2024 CHARLES POWELL

Contact Information

Contractor Calcons Inc; Lic. No.: 1077157-B 9400 CATTARAUGUS AVE      LOS ANGELES, CA 90034
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/19/2024 Corrections Issued STEPHANIE SWANSON
Underground Mechanical 3/19/2024 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 3/21/2024 Not Ready for Inspection MEL KHACHATOURIAN
Underground Mechanical 3/21/2024 Partial Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 3/22/2024 Approved ASHLEY THOMPSON
Pre-Inspection 4/4/2024 Partial Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 4/8/2024 Partial Approval ASHLEY THOMPSON
PLUMBING-Rough 5/14/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 6/5/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Partial Approval KIRK SANDERS
PLUMBING-Rough 6/5/2024 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 6/14/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 6/14/2024 Approved CARLOS MATAMOROS
Green Building Rough 6/14/2024 Approved CARLOS MATAMOROS
HVAC-Rough 6/14/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 6/14/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 6/14/2024 Approved CARLOS MATAMOROS
Wood Frame 6/14/2024 Approved CARLOS MATAMOROS
Insulation 7/2/2024 Approved KIRK SANDERS
Drywall Nailing 7/15/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 7/15/2024 Approved KEVIN SARGSYAN
Shower Pan 7/15/2024 Approved KEVIN SARGSYAN
Final 12/6/2024 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 12/6/2024 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 12/6/2024 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 12/6/2024 Not Ready for Inspection CHRISTOPHER WILSON
Final 12/11/2024 Corrections Issued KIRK SANDERS
Green Building Final 12/11/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 12/11/2024 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 12/11/2024 Approved KIRK SANDERS
Final 1/14/2025 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/14/2025 SGSOV Not Ready KEVIN SARGSYAN
Final 3/12/2025 OK to Issue CofO KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Approved KIRK SANDERS