1135 1/2 S 3RD AVE 90019

Certificate Information: 1135 1/2 S 3RD AVE 90019

Application / Permit
24016-30000-00990
Plan Check / Job No.
B24WL00080
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD THREE SPIRAL STAIRS TO AN EXISTING ADU TO ACCESS THREE NEW SEPARATED MEZANINES.
Permit Issued
Issued on 4/5/2024
Issuing Office
Metro
Current Status
Issued on 4/5/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/11/2024 APPLICANT
Assigned to Plan Check Engineer 1/13/2024 JAHANSHAH POURHASSAN
Corrections Issued 1/13/2024 JAHANSHAH POURHASSAN
Building Plans Picked Up 1/24/2024 APPLICANT
Applicant returned to address corrections 3/8/2024 CAROLEAN BASMA
Plan Check Approved 3/22/2024 CAROLEAN BASMA
Issued 4/5/2024 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 2/22/2024 JUSTIN BICOL
Tenant Habitability Plan Cleared 2/22/2024 ISMAEL HERNANDEZ
Certificate of Compliance Cleared 2/23/2024 MAYELA VILLA
Eng Process Fee Ord 176,300 Cleared 2/27/2024 JUSTIN BICOL
HPOZ Cleared 3/14/2024 SUKI GERSHENHORN

Contact Information

Architect Chun,, Youngmin; Lic. No.: C32890 1828 LINCOLN BLVD #B      SANTA MONICA, CA 90404
Contractor S M X Development; Lic. No.: 1027521-B 3579 E FOOTHILL BLVD #280      PASADENA, CA 91107
Engineer Lin,, Jason; Lic. No.: S6095 801 CREST VISTA DR      MONTEREY PARK, CA 91754

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/2/2024 Partial Inspection ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 6/6/2024 Approved WILLIAM MICHALAK
Footing/Foundation/Slab 6/6/2024 Partial Approval WILLIAM MICHALAK
METHANE-Barrier 6/6/2024 Approved WILLIAM MICHALAK
METHANE-Subgrade 6/6/2024 Approved WILLIAM MICHALAK
Pre-Inspection 6/6/2024 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 6/20/2024 Corrections Issued WILLIAM MICHALAK
Green Building Rough 6/20/2024 Not Ready for Inspection WILLIAM MICHALAK
METHANE-Rough 6/20/2024 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 7/9/2024 Corrections Issued WILLIAM MICHALAK
PLUMBING-Rough 7/9/2024 Corrections Issued WILLIAM MICHALAK
Wood Frame 7/9/2024 Corrections Issued WILLIAM MICHALAK
ELECTRICAL-Final 7/26/2024 Not Ready for Inspection WILLIAM MICHALAK
PLUMBING-Final 7/26/2024 Corrections Issued WILLIAM MICHALAK
Wood Frame 7/26/2024 Not Ready for Inspection WILLIAM MICHALAK
PLUMBING-Rough 8/1/2024 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 8/14/2024 Not Ready for Inspection WILLIAM MICHALAK
Final 8/14/2024 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 8/14/2024 Corrections Issued WILLIAM MICHALAK
Green Building Final 8/14/2024 Approved WILLIAM MICHALAK
Green Building Rough 8/14/2024 Corrections Issued WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 8/14/2024 SGSOV Not Ready WILLIAM MICHALAK
Smoke Detectors 8/14/2024 Corrections Issued WILLIAM MICHALAK
BUILDING-Rough-Frame 8/22/2024 Not Ready for Inspection WILLIAM MICHALAK
Final 8/22/2024 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 8/22/2024 Corrections Issued WILLIAM MICHALAK
Green Building Rough 8/22/2024 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 8/22/2024 SGSOV Approved WILLIAM MICHALAK
Smoke Detectors 8/22/2024 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 9/18/2024 Approved WILLIAM MICHALAK
Final 9/18/2024 Not Ready for Inspection WILLIAM MICHALAK
Footing/Foundation/Slab 9/18/2024 Approved WILLIAM MICHALAK
Green Building Rough 9/18/2024 Approved WILLIAM MICHALAK
Final 9/25/2024 Conditional Approval WILLIAM MICHALAK