4941 N GENTRY AVE 91607
Certificate Information: 4941 N GENTRY AVE 91607
- Application / Permit
- 24016-20001-19202
- Plan Check / Job No.
- B24VN24906
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT TO 24016-20000-19202. GARAGE CONVERSION & ADDITION SUPPLEMENTAL CHANGE TO DOCUMENT THE UNPERMITTED REAR ADDITION; ADD A CLOSET TO THE NEW BEDROOM, INTERCONNECT LAUNDRY ROOM W/ ADU, RELOCATE BEDROOM
- Permit Issued
- Issued on 1/4/2025
- Issuing Office
- Current Status
- Permit Finaled on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 12/14/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 12/31/2024 | NEHEMIAS RAMOS |
| Issued | 1/4/2025 | APPLICANT |
| Permit Finaled-Status Void | 4/7/2026 | SCOTT SHUSTER |
| Permit Finaled | 4/7/2026 | SCOTT SHUSTER |
| Re-Activate Permit | 5/28/2026 | SCOTT SHUSTER |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/23/2024 | JOANNA MARROQUIN |
Contact Information
| Architect | Driscoll,, Christopher; Lic. No.: NA36073 | , |
| Architect | Driscoll,, Christopher; Lic. No.: NA36073 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/18/2025 | Partial Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 3/6/2025 | Partial Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 3/19/2025 | Partial Approval | SCOTT SHUSTER |
| Footing/Foundation/Slab | 4/17/2025 | Partial Approval | SCOTT SHUSTER |
| Footing/Foundation/Slab | 5/1/2025 | Partial Inspection | SCOTT SHUSTER |
| Pre-Inspection | 5/20/2025 | Partial Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 5/29/2025 | Partial Approval | SCOTT SHUSTER |
| Footing/Foundation/Slab | 6/3/2025 | Partial Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 6/13/2025 | Partial Approval | SCOTT SHUSTER |
| ELECTRICAL-Rough | 6/13/2025 | Partial Approval | SCOTT SHUSTER |
| Green Building Rough | 6/13/2025 | Partial Approval | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 6/20/2025 | Partial Inspection | JOSE RUBIO |
| Insulation | 6/20/2025 | Partial Inspection | JOSE RUBIO |
| Interior/Exterior Lathing | 6/20/2025 | Partial Inspection | JOSE RUBIO |
| Drywall Nailing | 6/26/2025 | Partial Approval | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 4/7/2026 | Approved | SCOTT SHUSTER |
| Final | 4/7/2026 | Permit Finaled | SCOTT SHUSTER |
| Footing/Foundation/Slab | 4/7/2026 | Approved | SCOTT SHUSTER |
| Green Building Final | 4/7/2026 | Approved | SCOTT SHUSTER |
| Green Building Rough | 4/7/2026 | Approved | SCOTT SHUSTER |