7358 N BALCOM AVE 91335

Certificate Information: 7358 N BALCOM AVE 91335

Application / Permit
24016-20000-40450
Plan Check / Job No.
B24VN26906
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22. COMPLY WITH DEPARTMENT ORDER effective date 01/02/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 3/4/2025
Issuing Office
Valley
Current Status
CofO Issued on 2/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2024 APPLICANT
Assigned to Plan Check Engineer 1/2/2025 JEROME MAGAT PALMA
Corrections Issued 1/7/2025 JEROME MAGAT PALMA
Building Plans Picked Up 1/13/2025 APPLICANT
Plan Check Approved 3/4/2025 YAQUB MIRZA
Issued 3/4/2025 APPLICANT
CofO in Progress 9/26/2025 ROBERT GOLD
No Progress 9/29/2025 ROBERT GOLD
CofO in Progress 9/29/2025 ROBERT GOLD
Permit Finaled 2/18/2026 JOHN JANSON
CofO Issued 2/18/2026 JOHN JANSON
Permit Finaled 2/18/2026 JOHN JANSON

Permit Application Clearance Information

Miscellaneous Cleared 1/14/2025 ASHLEY RODARTE
Address approval Cleared 2/20/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 2/20/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/20/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/25/2025 Conditional Approval PTOLEMY HILL
Footing/Foundation/Slab 3/27/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 3/27/2025 Partial Approval ARUTYUN MADATYAN
Pre-Inspection 3/27/2025 Corrections Issued ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Partial Approval ARUTYUN MADATYAN
ELECTRICAL-Rough 4/24/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 4/24/2025 Partial Approval ARUTYUN MADATYAN
PLUMBING-Rough 4/24/2025 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 5/1/2025 Corrections Issued ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/6/2025 Approved ARUTYUN MADATYAN
Green Building Rough 5/6/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 5/6/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 5/6/2025 Approved ARUTYUN MADATYAN
Insulation 5/8/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 5/12/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 5/16/2025 Approved SCOTT SOBEL
Shower Pan 5/16/2025 Approved SCOTT SOBEL
PLUMBING-Rough 5/28/2025 Partial Approval ARUTYUN MADATYAN
Sewer 5/28/2025 Approved ARUTYUN MADATYAN
Final 7/2/2025 Corrections Issued ROBERT GOLD
Green Building Final 7/2/2025 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Not Ready ROBERT GOLD
Smoke Detectors 7/2/2025 Approved ROBERT GOLD
Final 9/26/2025 OK to Issue CofO ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 9/26/2025 SGSOV Approved ROBERT GOLD