7358 N BALCOM AVE 91335
Certificate Information: 7358 N BALCOM AVE 91335
- Application / Permit
- 24016-20000-40450
- Plan Check / Job No.
- B24VN26906
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22. COMPLY WITH DEPARTMENT ORDER effective date 01/02/2025. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 3/4/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 1/7/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/13/2025 | APPLICANT |
| Plan Check Approved | 3/4/2025 | YAQUB MIRZA |
| Issued | 3/4/2025 | APPLICANT |
| CofO in Progress | 9/26/2025 | ROBERT GOLD |
| No Progress | 9/29/2025 | ROBERT GOLD |
| CofO in Progress | 9/29/2025 | ROBERT GOLD |
| Permit Finaled | 2/18/2026 | JOHN JANSON |
| CofO Issued | 2/18/2026 | JOHN JANSON |
| Permit Finaled | 2/18/2026 | JOHN JANSON |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/14/2025 | ASHLEY RODARTE |
| Address approval | Cleared | 2/20/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 2/20/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/25/2025 | Conditional Approval | PTOLEMY HILL |
| Footing/Foundation/Slab | 3/27/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/27/2025 | Partial Approval | ARUTYUN MADATYAN |
| Pre-Inspection | 3/27/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Partial Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 4/24/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 4/24/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/24/2025 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/1/2025 | Corrections Issued | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 5/6/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 5/6/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 5/6/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/6/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 5/8/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 5/12/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 5/16/2025 | Approved | SCOTT SOBEL |
| Shower Pan | 5/16/2025 | Approved | SCOTT SOBEL |
| PLUMBING-Rough | 5/28/2025 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 5/28/2025 | Approved | ARUTYUN MADATYAN |
| Final | 7/2/2025 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 7/2/2025 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV Not Ready | ROBERT GOLD |
| Smoke Detectors | 7/2/2025 | Approved | ROBERT GOLD |
| Final | 9/26/2025 | OK to Issue CofO | ROBERT GOLD |