4613-4615 N WINNETKA CIR 91364

Certificate Information: 4613-4615 N WINNETKA CIR 91364

Application / Permit
24016-20000-40251
Plan Check / Job No.
B24VN26623
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) GARAGE AND PORTION OF (E) 2 STORY SFD ON 1ST FLOOR TO ACCESSORY DWELLING UNIT PERCA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 1/15/2025
Issuing Office
Valley
Current Status
CofO Issued on 9/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2024 APPLICANT
Assigned to Plan Check Engineer 12/31/2024 KAMYAR EMAMI
Corrections Issued 12/31/2024 KAMYAR EMAMI
Building Plans Picked Up 12/31/2024 APPLICANT
Plan Check Approved 1/15/2025 OMAR GARNICA
Issued 1/15/2025 APPLICANT
CofO in Progress 8/25/2025 MORRIS JACKSON
Permit Finaled 9/17/2025 JOHN JANSON
CofO Issued 9/17/2025 JOHN JANSON
Permit Finaled 9/17/2025 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/3/2025 CHARLES POWELL
Address approval Cleared 1/6/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/6/2025 LEE GUILBEAUX
Sewer availability Cleared 1/6/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/6/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/2/2025 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 6/10/2025 Approved JOHN KIDWELL
BUILDING-Rough-Frame 6/24/2025 Corrections Issued JOHN HAYES
Green Building Rough 6/24/2025 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/30/2025 Corrections Issued JOHN HAYES
Green Building Rough 6/30/2025 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/7/2025 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 7/7/2025 Not Ready for Inspection JOHN HAYES
Green Building Rough 7/7/2025 Not Ready for Inspection JOHN HAYES
HVAC-Rough 7/7/2025 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 7/7/2025 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/9/2025 Partial Approval JOHN HAYES
ELECTRICAL-Rough 7/9/2025 Approved JOHN HAYES
Green Building Rough 7/9/2025 Not Ready for Inspection JOHN HAYES
HVAC-Rough 7/9/2025 Approved JOHN HAYES
PLUMBING-Rough 7/9/2025 Approved JOHN HAYES
Insulation 7/14/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 7/14/2025 Approved SCOTT SOBEL
Drywall Nailing 7/23/2025 Approved JOHN HAYES
BUILDING-Rough-Frame 8/4/2025 Approved JOHN HAYES
Green Building Rough 8/4/2025 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/4/2025 SGSOV Not Ready JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/11/2025 SGSOV Not Ready JOHN HAYES
Pre-Inspection 8/12/2025 Corrections Issued MORRIS JACKSON
Final 8/25/2025 OK to Issue CofO MORRIS JACKSON
Green Building Final 8/25/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 8/25/2025 SGSOV Approved MORRIS JACKSON
Smoke Detectors 8/25/2025 Approved MORRIS JACKSON