10145 N WHEATLAND AVE 91040

Certificate Information: 10145 N WHEATLAND AVE 91040

Application / Permit
24016-20000-40198
Plan Check / Job No.
B24VN26565
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan CONVERT EXISTING DETACHED GARAGE TO ADU WITH 15.12 SF ADDITION PER LAMC 12.22 A.33(c)-(d), (g). "COMPLY WITH DEPARTMENT ORDER effective date 03/31/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 2/19/2025
Issuing Office
Current Status
CofO Issued on 7/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2024 APPLICANT
Assigned to Plan Check Engineer 12/30/2024 SAMUEL GONZALEZ
Corrections Issued 12/31/2024 SAMUEL GONZALEZ
Applicant returned to address corrections 2/1/2025 SAMUEL GONZALEZ
Plan Check Approved 2/19/2025 CRYSTEL MAALOUF
Issued 2/19/2025 APPLICANT
CofO in Progress 7/2/2025 WILLIAM WREN
Permit Finaled 7/25/2025 RUBEN SALAS
CofO Issued 7/25/2025 RUBEN SALAS
Permit Finaled 7/25/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/13/2025 EDGAR ALCARAZ
BHO/Hillside ordinance Cleared 1/13/2025 EDGAR ALCARAZ
BHO/Hillside ordinance Cleared 1/13/2025 EDGAR ALCARAZ
BHO/Hillside ordinance Cleared 1/13/2025 EDGAR ALCARAZ
BHO/Hillside ordinance Cleared 1/13/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/14/2025 EDGAR ALCARAZ
Specific Plan Cleared 1/15/2025 DANG NGUYEN
Grading Pre-Inspection Cleared 1/15/2025 CHARLES POWELL
Sewer availability Cleared 2/13/2025 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/28/2025 Conditional Approval ROBERT GOLD
Reinforced Concrete Frame 2/28/2025 Approved MICHAEL CORTEZ
PLUMBING-Rough 3/5/2025 Corrections Issued WILLIAM WREN
PLUMBING-Rough 3/7/2025 Partial Approval WILLIAM WREN
Sewer 3/7/2025 Approved WILLIAM WREN
Underground Mechanical 3/7/2025 Approved WILLIAM WREN
Pre-Inspection 3/17/2025 Partial Approval MATTHEW NELSON
Wood Frame 3/17/2025 Partial Approval MATTHEW NELSON
Pre-Inspection 3/19/2025 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 4/2/2025 Approved WILLIAM WREN
ELECTRICAL-Rough 4/2/2025 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 4/2/2025 Partial Approval WILLIAM WREN
PLUMBING-Rough 4/2/2025 Approved WILLIAM WREN
Insulation 4/7/2025 Approved WILLIAM WREN
Drywall Nailing 4/11/2025 Approved WILLIAM WREN
Green Building Rough 4/11/2025 Approved WILLIAM WREN
Shower Pan 4/11/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 4/15/2025 Approved WILLIAM WREN
Final 6/11/2025 Corrections Issued MATTHEW NELSON
Green Building Final 6/11/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/11/2025 SGSOV Approved MATTHEW NELSON
Smoke Detectors 6/11/2025 Approved MATTHEW NELSON
Final 6/16/2025 OK to Issue CofO WILLIAM WREN