8823 N SUNLAND BLVD 91352
Certificate Information: 8823 N SUNLAND BLVD 91352
- Application / Permit
- 24016-20000-40157
- Plan Check / Job No.
- B24VN26501
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Bank
- Work Description
- EPLAN Change of use from Restaurant to Bank. Interior tenant improvement only.
- Permit Issued
- Issued on 4/1/2025
- Issuing Office
- Current Status
- CofO Issued on 6/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | SINA KHOSRAVI |
| Assigned to Zoning Architect | 12/26/2024 | MEGAN KOLP |
| Corrections Issued | 1/8/2025 | MICHAEL LOPEZ |
| Quality Review Completed | 1/9/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 3/11/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 3/18/2025 | SINA KHOSRAVI |
| Plan Check Approved | 4/1/2025 | SINA KHOSRAVI |
| Issued | 4/1/2025 | APPLICANT |
| TCO Issued (Expire Date: 10-28-2026) | 5/1/2026 | RICKEY JACKSON |
| CofO in Progress | 6/17/2026 | JOHN KITCKO |
| Permit Finaled | 6/18/2026 | JEFFREY DURAN |
| CofO Issued | 6/18/2026 | JEFFREY DURAN |
| Permit Finaled | 6/18/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/10/2025 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2025 | CARLOS RAMIREZ |
| DAS Clearance | Cleared | 2/27/2025 | Tse-Ming Huang |
| Zoning Plan Check | Cleared | 3/7/2025 | MEGAN KOLP |
Contact Information
| Architect | Dong,, Heney; Lic. No.: NA9770 | , |
| Contractor | Parker Brown Inc; Lic. No.: 689613-B | , |
| Engineer | Lambert,, Will A; Lic. No.: NA5430 | , |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/30/2025 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 5/5/2025 | Corrections Issued | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/21/2025 | Partial Approval | ANDREW DORSO |
| Structural Steel Frame | 6/16/2025 | Partial Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 6/20/2025 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 7/2/2025 | Conditional Approval | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2025 | Partial Inspection | ANDREW DORSO |
| Insulation | 8/11/2025 | Approved | ANDREW DORSO |
| Wood Frame | 8/11/2025 | Partial Inspection | ANDREW DORSO |
| Deputy Wood Construction | 8/13/2025 | Conditional Approval | ANDREW DORSO |
| Light Gage Steel Frame | 8/13/2025 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 8/15/2025 | Approved | ANDREW DORSO |
| Drywall Nailing | 9/5/2025 | Approved | KENNETH ROBERTS |
| Light Gage Steel Frame | 9/11/2025 | Corrections Issued | JOHN KITCKO |
| Light Gage Steel Frame | 9/15/2025 | Approved | ANDREW DORSO |
| Drywall Nailing | 9/17/2025 | Approved | ANDREW DORSO |
| Interior/Exterior Lathing | 12/22/2025 | Approved | GREGORY POMISH |
| T-Bar Ceiling | 1/23/2026 | Approved | ANDREW DORSO |
| Pre-Inspection | 2/25/2026 | Partial Inspection | ANDREW DORSO |
| Final | 4/24/2026 | OK to Issue CofO | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 4/24/2026 | SGSOV No Gas | JOHN KITCKO |
| Smoke Detectors | 4/24/2026 | Not Ready for Inspection | JOHN KITCKO |