15105 W MONTE ST 91342
Certificate Information: 15105 W MONTE ST 91342
- Application / Permit
- 24016-20000-40145
- Plan Check / Job No.
- B24VN26483
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) .
- Permit Issued
- Issued on 1/3/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 12/30/2024 | MIROOSH KHACHATOORIAN |
| Building Plans Picked Up | 12/31/2024 | APPLICANT |
| Plan Check Approved | 1/3/2025 | ALEC MOUSAKHANIAN |
| Issued | 1/3/2025 | APPLICANT |
| CofO in Progress | 9/25/2025 | KEVIN BERBERYAN |
| No Progress | 9/29/2025 | RAUL OLAGI |
| CofO in Progress | 9/29/2025 | RAUL OLAGI |
| Permit Finaled | 10/14/2025 | RUBEN SALAS |
| CofO Issued | 10/14/2025 | RUBEN SALAS |
| Permit Finaled | 10/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/2/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/2/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 1/2/2025 | BIAINA HARITUNIAN |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/5/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 3/5/2025 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 3/24/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 3/26/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Partial Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/18/2025 | Corrections Issued | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/18/2025 | Partial Approval | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 4/18/2025 | Approved | RYAN SALAZAR |
| Sewer | 4/18/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 4/18/2025 | Approved | RYAN SALAZAR |
| Insulation | 4/21/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Insulation | 4/22/2025 | Approved | KEVIN BERBERYAN |
| Special/Order Compliance | 4/22/2025 | Partial Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2025 | Corrections Issued | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Partial Inspection | KEVIN BERBERYAN |
| Drywall Nailing | 5/6/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 5/14/2025 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/15/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 5/15/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/15/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 5/15/2025 | Approved | KEVIN BERBERYAN |
| Gas Test | 7/17/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 8/12/2025 | Corrections Issued | KEVIN BERBERYAN |
| Final | 8/28/2025 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 8/28/2025 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Not Ready | DAVID ANDERSON |
| Service/Power Release | 8/28/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 8/28/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 9/16/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 9/16/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/16/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/16/2025 | Approved | KEVIN BERBERYAN |