15105 W MONTE ST 91342

Certificate Information: 15105 W MONTE ST 91342

Application / Permit
24016-20000-40145
Plan Check / Job No.
B24VN26483
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) .
Permit Issued
Issued on 1/3/2025
Issuing Office
Valley
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2024 APPLICANT
Assigned to Plan Check Engineer 12/30/2024 MIROOSH KHACHATOORIAN
Corrections Issued 12/30/2024 MIROOSH KHACHATOORIAN
Building Plans Picked Up 12/31/2024 APPLICANT
Plan Check Approved 1/3/2025 ALEC MOUSAKHANIAN
Issued 1/3/2025 APPLICANT
CofO in Progress 9/25/2025 KEVIN BERBERYAN
No Progress 9/29/2025 RAUL OLAGI
CofO in Progress 9/29/2025 RAUL OLAGI
Permit Finaled 10/14/2025 RUBEN SALAS
CofO Issued 10/14/2025 RUBEN SALAS
Permit Finaled 10/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/2/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/2/2025 BIAINA HARITUNIAN
Sewer availability Cleared 1/2/2025 BIAINA HARITUNIAN

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/5/2025 Approved KEVIN BERBERYAN
Underground Mechanical 3/5/2025 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 3/24/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 3/26/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 4/18/2025 Corrections Issued RYAN SALAZAR
Interior/Exterior Lathing 4/18/2025 Partial Approval RYAN SALAZAR
Rough-Elec/Plmb/HVAC 4/18/2025 Approved RYAN SALAZAR
Sewer 4/18/2025 Approved RYAN SALAZAR
Underground Mechanical 4/18/2025 Approved RYAN SALAZAR
Insulation 4/21/2025 Not Ready for Inspection KEVIN BERBERYAN
Insulation 4/22/2025 Approved KEVIN BERBERYAN
Special/Order Compliance 4/22/2025 Partial Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Corrections Issued KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Partial Inspection KEVIN BERBERYAN
Drywall Nailing 5/6/2025 Approved KEVIN BERBERYAN
Shower Pan 5/14/2025 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 5/15/2025 Approved KEVIN BERBERYAN
Green Building Rough 5/15/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 5/15/2025 Approved KEVIN BERBERYAN
Shower Pan 5/15/2025 Approved KEVIN BERBERYAN
Gas Test 7/17/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 8/12/2025 Corrections Issued KEVIN BERBERYAN
Final 8/28/2025 Corrections Issued DAVID ANDERSON
Green Building Final 8/28/2025 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Not Ready DAVID ANDERSON
Service/Power Release 8/28/2025 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 8/28/2025 Not Ready for Inspection DAVID ANDERSON
Final 9/16/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 9/16/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 9/16/2025 Approved KEVIN BERBERYAN