6313-6315 E GARVANZA AVE 90042

Certificate Information: 6313-6315 E GARVANZA AVE 90042

Application / Permit
24016-20000-39872
Plan Check / Job No.
B24VN26243
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF (E) SINGLE FAMILY DWELLING TO JUNIOR ACCESSORY DWELLING UNIT (469 SF) PER GCS 66323(a)(1) AND 66333.
Permit Issued
Issued on 3/13/2025
Issuing Office
Valley
Current Status
CofO Issued on 5/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2024 APPLICANT
Assigned to Plan Check Engineer 12/27/2024 JESSE ARELLANO
Corrections Issued 1/2/2025 JESSE ARELLANO
Building Plans Picked Up 1/7/2025 APPLICANT
Applicant returned to address corrections 2/27/2025 GIOVANNY CHAVEZ
Plan Check Approved 3/13/2025 ALEC MOUSAKHANIAN
Issued 3/13/2025 APPLICANT
CofO in Progress 5/8/2025 ALIZAH MAYAGOITIA
Permit Finaled 5/10/2025 DEROLD HAUFF
CofO Issued 5/10/2025 DEROLD HAUFF
Permit Finaled 5/10/2025 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 1/30/2025 NATHALY DE LA PAZ
Address approval Cleared 2/18/2025 CARLOS RAMIREZ
Sewer availability Cleared 2/18/2025 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/19/2025 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 2/21/2025 MANUEL TEJADA

Contact Information

Contractor J & L Construction And Investments Inc; Lic. No.: 1028412-B 10750 REDMONT AVE      TUJUNGA, CA 91042

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/18/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 3/18/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 3/18/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 3/18/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 3/18/2025 Approved ALIZAH MAYAGOITIA
Insulation 3/21/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 3/21/2025 Approved JOSH MEISTER
Shower Pan 3/21/2025 Approved JOSH MEISTER
Drywall Nailing 3/25/2025 Approved ALIZAH MAYAGOITIA
Final 5/2/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 5/2/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 5/2/2025 Approved ALIZAH MAYAGOITIA
Final 5/6/2025 Partial Approval ALIZAH MAYAGOITIA
Final 5/8/2025 OK to Issue CofO ALIZAH MAYAGOITIA