6531-6533 N PETIT AVE 91406

Certificate Information: 6531-6533 N PETIT AVE 91406

Application / Permit
24016-20000-39857
Plan Check / Job No.
B24VN26223
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
Permit Issued
Issued on 9/19/2025
Issuing Office
Valley
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2024 APPLICANT
Assigned to Plan Check Engineer 12/27/2024 ARTIN ZARUKIAN
Corrections Issued 12/28/2024 ARTIN ZARUKIAN
Building Plans Picked Up 1/3/2025 APPLICANT
Plan Check Approved 9/19/2025 GIOVANNY CHAVEZ
Issued 9/19/2025 APPLICANT
CofO in Progress 2/12/2026 GAREN HAYRAPETYAN
Permit Finaled 3/3/2026 RUBEN SALAS
CofO Issued 3/3/2026 RUBEN SALAS
Permit Finaled 3/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/7/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 1/7/2025 BIAINA HARITUNIAN
Sewer availability Cleared 1/7/2025 BIAINA HARITUNIAN
ZI Cleared 1/8/2025 ALEX VELA
Watercourse Cleared 1/9/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/22/2025 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 9/23/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 9/23/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 10/15/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Rough 10/15/2025 Approved GAREN HAYRAPETYAN
Gas Test 10/15/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 10/15/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 10/15/2025 Conditional Approval GAREN HAYRAPETYAN
PLUMBING-Rough 10/15/2025 Corrections Issued GAREN HAYRAPETYAN
Sewer 10/15/2025 Approved GAREN HAYRAPETYAN
Gas Test 10/20/2025 Approved WAYNE REGESTER
HVAC-Rough 10/20/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 10/20/2025 Partial Approval WAYNE REGESTER
PLUMBING-Rough 10/20/2025 Approved WAYNE REGESTER
Shower Pan 10/20/2025 Approved WAYNE REGESTER
Wood Frame 10/20/2025 Approved WAYNE REGESTER
Insulation 10/23/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/28/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 10/28/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 11/3/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 11/3/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 2/4/2026 Approved GAREN HAYRAPETYAN
Final 2/4/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 2/4/2026 Approved GAREN HAYRAPETYAN
HVAC-Final 2/4/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 2/4/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 2/4/2026 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 2/4/2026 Approved GAREN HAYRAPETYAN
Final 2/12/2026 OK to Issue CofO GAREN HAYRAPETYAN