16631-16633 W OSBORNE ST 91343

Certificate Information: 16631-16633 W OSBORNE ST 91343

Application / Permit
24016-20000-39846
Plan Check / Job No.
B24VN26212
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 1/13/2025
Issuing Office
Current Status
CofO Issued on 9/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2024 APPLICANT
Assigned to Plan Check Engineer 12/27/2024 ARTIN ZARUKIAN
Corrections Issued 12/28/2024 ARTIN ZARUKIAN
Building Plans Picked Up 12/30/2024 APPLICANT
Plan Check Approved 1/13/2025 OMAR GARNICA
Issued 1/13/2025 APPLICANT
CofO in Progress 6/23/2025 SALVADOR MARTINEZ
CofO Issued 9/23/2025 RUBEN SALAS
Permit Finaled 9/23/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/30/2024 BIAINA HARITUNIAN
Sewer availability Cleared 12/30/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/31/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 1/8/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/27/2025 Partial Inspection SALVADOR MARTINEZ
Deputy Drilled-In Anchors 1/30/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 2/5/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 2/5/2025 Partial Approval SALVADOR MARTINEZ
Sewer 2/5/2025 Not Ready for Inspection SALVADOR MARTINEZ
Footing/Foundation/Slab 2/10/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 3/11/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 3/11/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 3/11/2025 Approved GAREN HAYRAPETYAN
Sewer 3/11/2025 Approved GAREN HAYRAPETYAN
Wood Frame 3/11/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 3/14/2025 Approved GAREN HAYRAPETYAN
Wood Frame 3/14/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 3/25/2025 Partial Approval SALVADOR MARTINEZ
Green Building Rough 3/25/2025 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 3/25/2025 Partial Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Approved SALVADOR MARTINEZ
Insulation 4/3/2025 Partial Approval SALVADOR MARTINEZ
Drywall Nailing 4/14/2025 Approved LOUIS ESCOTO
Green Building Rough 4/14/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 4/29/2025 Approved GAREN HAYRAPETYAN
Shower Pan 4/29/2025 Approved GAREN HAYRAPETYAN
Special/Order Compliance 4/29/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 6/9/2025 Approved MICHAEL CORTEZ
Final 6/9/2025 Corrections Issued MICHAEL CORTEZ
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV Approved MICHAEL CORTEZ
Service/Power Release 6/9/2025 Not Ready for Inspection MICHAEL CORTEZ
Smoke Detectors 6/9/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 6/18/2025 Approved SALVADOR MARTINEZ
Final 6/18/2025 OK to Issue CofO SALVADOR MARTINEZ
Green Building Final 6/18/2025 Approved SALVADOR MARTINEZ
HVAC-Final 6/18/2025 Approved SALVADOR MARTINEZ
PLUMBING-Final 6/18/2025 Approved SALVADOR MARTINEZ