4106 3/4 S DENKER AVE 90062
Certificate Information: 4106 3/4 S DENKER AVE 90062
- Application / Permit
- 24016-20000-39643
- Plan Check / Job No.
- B24VN25960
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO A NEW DETACHED ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 2/25/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 12/26/2024 | MIROOSH KHACHATOORIAN |
| Issued | 2/25/2025 | APPLICANT |
| CofO in Progress | 2/20/2026 | SABAS ALONSO |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| CofO Issued | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/31/2024 | WALLIE JONG |
| Sewer availability | Cleared | 12/31/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2025 | WALLIE JONG |
| Construction near power lines | Cleared | 2/18/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/18/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Vision Adu Llc; Lic. No.: 1115842-B | 405 S MISSION DR SAN GABRIEL, CA 91776 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/13/2025 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 3/13/2025 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 3/13/2025 | Partial Approval | SABAS ALONSO |
| Sewer | 4/1/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/1/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 4/4/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 4/4/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 4/8/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 4/8/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 4/8/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 4/18/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 4/18/2025 | Corrections Issued | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/22/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 4/22/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 4/22/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 4/22/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 4/22/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/25/2025 | Corrections Issued | SABAS ALONSO |
| Sewer | 4/25/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/25/2025 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/28/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/28/2025 | Approved | SABAS ALONSO |
| Sewer | 4/28/2025 | Approved | SABAS ALONSO |
| Insulation | 4/29/2025 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/5/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 5/14/2025 | No Access for Inspection | ANTHONY RAMOS |
| Shower Pan | 5/14/2025 | No Access for Inspection | ANTHONY RAMOS |
| Interior/Exterior Lathing | 5/15/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 5/15/2025 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 7/1/2025 | Partial Approval | LUIS CASTRO |
| Final | 7/28/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 7/28/2025 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 7/28/2025 | Approved | SABAS ALONSO |
| Final | 10/24/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 10/24/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 1/21/2026 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 1/21/2026 | Approved | SABAS ALONSO |
| Final | 2/2/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Final | 2/17/2026 | Corrections Issued | SABAS ALONSO |
| Final | 2/19/2026 | OK to Issue CofO | SABAS ALONSO |