14016 W FILMORE ST 91331
Certificate Information: 14016 W FILMORE ST 91331
- Application / Permit
- 24016-20000-39394
- Plan Check / Job No.
- B24VN25742
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED STORAGE BLDG W/ ATTACHED CARPORT INTO A (N) 940 SF ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) CONSTRUCTION DESIGN PER ENGR.
- Permit Issued
- Issued on 1/6/2025
- Issuing Office
- Valley
- Current Status
- Issued on 1/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 12/21/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 12/23/2024 | APPLICANT |
| Issued | 1/6/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/31/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 12/31/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/31/2024 | BIAINA HARITUNIAN |
| ZA Case | Cleared | 1/2/2025 | ALEX VELA |
| ZA Case | Cleared | 1/2/2025 | ALEX VELA |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/20/2025 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/20/2025 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 2/20/2025 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 2/20/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/20/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 4/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/7/2025 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 4/7/2025 | Approved | RAUL OLAGI |
| HVAC-Rough | 4/7/2025 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 4/7/2025 | Approved | RAUL OLAGI |
| Special/Order Compliance | 4/8/2025 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/15/2025 | Not Ready for Inspection | RAUL OLAGI |
| Green Building Rough | 4/15/2025 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 4/15/2025 | Partial Approval | RAUL OLAGI |
| MERV13>=Rough | 4/15/2025 | Approved | RAUL OLAGI |
| METHANE-Rough | 4/15/2025 | Approved | RAUL OLAGI |
| Shower Pan | 4/15/2025 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/22/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 4/22/2025 | Approved | JACK KARGODORIAN |
| Insulation | 4/28/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 5/1/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Drywall Nailing | 5/6/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 5/6/2025 | Partial Approval | MICHAEL CORTEZ |
| SGSOV-Seismic Gas S/O Valve | 12/10/2025 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Final | 12/19/2025 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 12/19/2025 | Not Ready for Inspection | RAUL OLAGI |
| MERV13>=Final | 12/19/2025 | Not Ready for Inspection | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 12/19/2025 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Final | 1/2/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/2/2026 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 1/2/2026 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/2/2026 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/30/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 4/30/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 4/30/2026 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 4/30/2026 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 4/30/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/30/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/30/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 4/30/2026 | Approved | JENNIFER RABUCHIN |