6028-6030 N MANTON AVE 91367
Certificate Information: 6028-6030 N MANTON AVE 91367
- Application / Permit
- 24016-20000-39364
- Plan Check / Job No.
- B24VN25685
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 1/7/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 12/21/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/27/2024 | APPLICANT |
| Plan Check Approved | 1/7/2025 | SERGIO MUNIZ |
| Issued | 1/7/2025 | APPLICANT |
| CofO in Progress | 4/25/2025 | TROY SANDERS |
| Permit Finaled | 5/28/2025 | JOHN JANSON |
| CofO Issued | 5/28/2025 | JOHN JANSON |
| Permit Finaled | 5/28/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2024 | KEVIN CHUNG |
| Sewer availability | Cleared | 12/23/2024 | KEVIN CHUNG |
| Eng Process Fee Ord 176,300 | Cleared | 12/26/2024 | KEVIN CHUNG |
| Grading Pre-Inspection | Cleared | 12/27/2024 | ROBERT PINA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2025 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 2/24/2025 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 3/5/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 3/5/2025 | Approved | TROY SANDERS |
| Green Building Rough | 3/5/2025 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 3/5/2025 | Approved | TROY SANDERS |
| Insulation | 3/7/2025 | Approved | TROY SANDERS |
| Drywall Nailing | 3/13/2025 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 4/18/2025 | Approved | GEVORK IPCHYAN |
| Final | 4/18/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 4/18/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Rough | 4/18/2025 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2025 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 4/18/2025 | Approved | GEVORK IPCHYAN |
| Final | 4/23/2025 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 4/23/2025 | Approved | TROY SANDERS |
| Final | 4/25/2025 | OK to Issue CofO | TROY SANDERS |