23103 W VANOWEN ST 91307

Certificate Information: 23103 W VANOWEN ST 91307

Application / Permit
24016-20000-39309
Plan Check / Job No.
B24VN25640
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 8/15/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 JESSE ARELLANO
Corrections Issued 12/21/2024 JESSE ARELLANO
Building Plans Picked Up 12/23/2024 APPLICANT
Plan Check Approved 12/30/2024 MOHAMMAD ESMAILI
Issued 8/15/2025 APPLICANT
CofO in Progress 4/8/2026 GEVORK IPCHYAN
Permit Finaled 4/10/2026 JOHN JANSON
CofO Issued 4/10/2026 JOHN JANSON
Permit Finaled 4/10/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/24/2024 KEVIN CHUNG
Roof/Waste drainage to street Cleared 12/24/2024 KEVIN CHUNG
Sewer availability Cleared 12/24/2024 KEVIN CHUNG
Eng Process Fee Ord 176,300 Cleared 12/27/2024 EDGAR ALCARAZ

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/18/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 8/19/2025 Corrections Issued GEVORK IPCHYAN
Deputy Drilled-In Anchors 8/21/2025 Conditional Approval TROY SANDERS
Footing/Foundation/Slab 8/22/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 9/9/2025 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 9/9/2025 Partial Approval GEVORK IPCHYAN
Wood Frame 9/9/2025 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 10/2/2025 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 10/2/2025 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 10/2/2025 Not Ready for Inspection GEVORK IPCHYAN
Wood Frame 10/2/2025 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Rough 10/15/2025 Approved GEVORK IPCHYAN
HVAC-Rough 10/15/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 10/15/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 11/3/2025 Approved GEVORK IPCHYAN
Green Building Rough 11/3/2025 Approved GEVORK IPCHYAN
HVAC-Rough 11/3/2025 Approved GEVORK IPCHYAN
Insulation 11/3/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 11/3/2025 Partial Approval GEVORK IPCHYAN
Drywall Nailing 11/19/2025 Approved GEVORK IPCHYAN
Shower Pan 11/19/2025 Approved GEVORK IPCHYAN
Underground Mechanical 2/9/2026 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 3/3/2026 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 3/3/2026 Approved GEVORK IPCHYAN
Underground Mechanical 3/3/2026 Approved GEVORK IPCHYAN
ELECTRICAL-Final 3/13/2026 Approved GEVORK IPCHYAN
Final 3/13/2026 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Final 3/13/2026 Approved GEVORK IPCHYAN
ELECTRICAL-Final 4/7/2026 Approved GEVORK IPCHYAN
Final 4/7/2026 OK to Issue CofO GEVORK IPCHYAN
Green Building Final 4/7/2026 Approved GEVORK IPCHYAN
HVAC-Final 4/7/2026 Approved GEVORK IPCHYAN
PLUMBING-Final 4/7/2026 Approved GEVORK IPCHYAN
Service/Power Release 4/7/2026 Approved GEVORK IPCHYAN