6204 N PEACH AVE 91411

Certificate Information: 6204 N PEACH AVE 91411

Application / Permit
24016-20000-39242
Plan Check / Job No.
B24VN25554
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/14/2025
Issuing Office
Valley
Current Status
CofO Issued on 12/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 JESSE ARELLANO
Corrections Issued 12/21/2024 JESSE ARELLANO
Building Plans Picked Up 1/6/2025 APPLICANT
Applicant returned to address corrections 2/13/2025 ALEC MOUSAKHANIAN
Issued 2/14/2025 APPLICANT
CofO in Progress 11/18/2025 MISAEL ESPARZA
Permit Finaled 12/24/2025 RUBEN SALAS
CofO Issued 12/24/2025 RUBEN SALAS
Permit Finaled 12/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/7/2025 CARLOS RAMIREZ
Construction near power lines Cleared 1/7/2025 EDGAR PASCUA
Sewer availability Cleared 1/7/2025 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 1/9/2025 CARLOS RAMIREZ
ZI Cleared 1/24/2025 MATHEW QUAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/2/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 5/2/2025 Approved RYAN SALAZAR
PLUMBING-Rough 5/2/2025 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 6/23/2025 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 6/23/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Partial Approval RYAN SALAZAR
Green Building Rough 6/23/2025 Approved RYAN SALAZAR
HVAC-Rough 6/23/2025 Approved RYAN SALAZAR
PLUMBING-Rough 6/23/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/10/2025 Approved RYAN SALAZAR
Insulation 7/10/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/10/2025 Partial Approval RYAN SALAZAR
Underground Mechanical 7/10/2025 Approved RYAN SALAZAR
Drywall Nailing 7/25/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 7/25/2025 Approved GAREN HAYRAPETYAN
Shower Pan 7/25/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/6/2025 Approved OGANES TARAKHCHYAN
Final 11/6/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 11/6/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 11/6/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 11/6/2025 Approved OGANES TARAKHCHYAN
Final 11/17/2025 OK to Issue CofO MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/17/2025 SGSOV Approved MISAEL ESPARZA
Service/Power Release 11/17/2025 Approved MISAEL ESPARZA