6204 N PEACH AVE 91411
Certificate Information: 6204 N PEACH AVE 91411
- Application / Permit
- 24016-20000-39242
- Plan Check / Job No.
- B24VN25554
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/14/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | JESSE ARELLANO |
| Corrections Issued | 12/21/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 1/6/2025 | APPLICANT |
| Applicant returned to address corrections | 2/13/2025 | ALEC MOUSAKHANIAN |
| Issued | 2/14/2025 | APPLICANT |
| CofO in Progress | 11/18/2025 | MISAEL ESPARZA |
| Permit Finaled | 12/24/2025 | RUBEN SALAS |
| CofO Issued | 12/24/2025 | RUBEN SALAS |
| Permit Finaled | 12/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2025 | CARLOS RAMIREZ |
| Construction near power lines | Cleared | 1/7/2025 | EDGAR PASCUA |
| Sewer availability | Cleared | 1/7/2025 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2025 | CARLOS RAMIREZ |
| ZI | Cleared | 1/24/2025 | MATHEW QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/2/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/2/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 5/2/2025 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 6/23/2025 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 6/23/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 6/23/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 6/23/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 6/23/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2025 | Approved | RYAN SALAZAR |
| Insulation | 7/10/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/10/2025 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 7/10/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/25/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 7/25/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 7/25/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 11/6/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 11/6/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 11/6/2025 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/6/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 11/6/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 11/17/2025 | OK to Issue CofO | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 11/17/2025 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 11/17/2025 | Approved | MISAEL ESPARZA |