6557 N MCLENNAN AVE 91406

Certificate Information: 6557 N MCLENNAN AVE 91406

Application / Permit
24016-20000-39188
Plan Check / Job No.
B24VN25502
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan Replace fire damaged portions of SFD and add new Trellis with deck and installing NFPA13D fire sprinklers
Permit Issued
Issued on 2/5/2025
Issuing Office
Current Status
Issued on 2/5/2025

Permit Application Status History

Submitted 1/3/2025 APPLICANT
Assigned to Plan Check Engineer 1/8/2025 NEHEMIAS RAMOS
Corrections Issued 1/9/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 1/16/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 1/30/2025 NEHEMIAS RAMOS
Plan Check Approved 2/4/2025 NEHEMIAS RAMOS
Issued 2/5/2025 APPLICANT

Permit Application Clearance Information

ZI Cleared 1/9/2025 ASHLEY RODARTE
Eng Process Fee Ord 176,300 Cleared 1/16/2025 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 1/16/2025 EDGAR ALCARAZ

Contact Information

Contractor Brown K B Construction Company; Lic. No.: 385923-B       ,
Contractor K B Construction Co; Lic. No.: 385923-B       ,
Engineer Ionescu,, Benjamin; Lic. No.: NA65482       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2025 Partial Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Corrections Issued JACK KARGODORIAN
Pre-Inspection 4/21/2025 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Partial Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 6/13/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 6/13/2025 Corrections Issued SALVADOR MARTINEZ
Gas Test 6/13/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 6/13/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 9/8/2025 Approved WAYNE REGESTER
ELECTRICAL-Rough 10/9/2025 Approved WAYNE REGESTER
Footing/Foundation/Slab 10/9/2025 Approved WAYNE REGESTER
PLUMBING-Rough 10/9/2025 Approved WAYNE REGESTER
Sewer 10/9/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 10/27/2025 Corrections Issued GAREN HAYRAPETYAN
HVAC-Rough 11/7/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 11/7/2025 Partial Approval GAREN HAYRAPETYAN
Wood Frame 11/7/2025 Partial Approval GAREN HAYRAPETYAN
Gas Test 11/12/2025 Approved GAREN HAYRAPETYAN
Insulation 11/12/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 12/8/2025 Approved MICHAEL CORTEZ
Drywall Nailing 12/9/2025 No Access for Inspection MICHAEL CORTEZ
Service/Power Release 1/8/2026 Corrections Issued GAREN HAYRAPETYAN
BUILDING-Rough-Frame 5/22/2026 Partial Approval MICHAEL CORTEZ
Pre-Inspection 6/5/2026 Partial Inspection MICHAEL CORTEZ
Final 7/7/2026 Corrections Issued MICHAEL CORTEZ
SGSOV-Seismic Gas S/O Valve 7/7/2026 SGSOV Not Ready MICHAEL CORTEZ
Smoke Detectors 7/7/2026 Approved MICHAEL CORTEZ