15711 W ROSCOE BLVD 91343
Certificate Information: 15711 W ROSCOE BLVD 91343
- Application / Permit
- 24016-20000-39082
- Plan Check / Job No.
- B24VN25385
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- E-plan. Tenant improvement of existing hotel for interim supportive housing. Including new office space, laundry room and break breakroom. Project Homekey.
- Permit Issued
- Issued on 3/13/2025
- Issuing Office
- Current Status
- Issued on 3/13/2025
Permit Application Status History
| Submitted | 12/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | SALVADOR QUINTANILLA |
| Assigned to Zoning Architect | 12/19/2024 | LY CHEA |
| Corrections Issued | 12/21/2024 | SALVADOR QUINTANILLA |
| Quality Review Completed | 12/23/2024 | PETER KIM |
| Applicant returned to address corrections | 1/13/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/14/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/17/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/31/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 3/6/2025 | SALVADOR QUINTANILLA |
| Plan Check Approved | 3/11/2025 | SALVADOR QUINTANILLA |
| Issued | 3/13/2025 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/8/2025 | MAYELA VILLA |
| ZA Case | Cleared | 1/8/2025 | MAYELA VILLA |
| Miscellaneous | Cleared | 2/4/2025 | DANIEL CORONADO |
| DAS Clearance | Cleared | 3/7/2025 | Cristina Salazar |
| Zoning Plan Check | Cleared | 3/10/2025 | Cristina Salazar |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/25/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 7/15/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Wood Frame | 7/21/2025 | Partial Approval | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 7/28/2025 | Partial Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 7/28/2025 | Partial Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 7/30/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Special/Order Compliance | 7/30/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 7/31/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Wood Frame | 8/8/2025 | Corrections Issued | DEANDRE HOFFMAN |
| Pre-Inspection | 8/15/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Insulation | 9/15/2025 | Partial Approval | DEANDRE HOFFMAN |
| Wood Frame | 9/15/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 9/22/2025 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 9/22/2025 | Partial Approval | GREGORY POMISH |
| Insulation | 9/26/2025 | Partial Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 10/10/2025 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 10/21/2025 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 10/29/2025 | Conditional Approval | JEFFREY DURAN |
| Excavation/Setback/Form/Re-Bar | 10/30/2025 | Partial Approval | KENNETH ROBERTS |
| Pre-Inspection | 10/30/2025 | Approved | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 11/3/2025 | Conditional Approval | KENNETH ROBERTS |
| Excavation/Setback/Form/Re-Bar | 12/12/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 12/12/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 12/16/2025 | Conditional Approval | JEFFREY DURAN |
| Excavation/Setback/Form/Re-Bar | 12/16/2025 | Not Ready for Inspection | JOHN KITCKO |
| Special/Order Compliance | 12/16/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Drywall Nailing | 12/24/2025 | Partial Approval | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 1/23/2026 | Approved | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2026 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 2/11/2026 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 2/12/2026 | Partial Approval | EDWIN GREGORYONA |
| Deputy Wood Construction | 2/20/2026 | Partial Approval | EDWIN GREGORYONA |
| Insulation | 2/26/2026 | Partial Inspection | EDWIN GREGORYONA |
| Wood Frame | 2/26/2026 | Partial Inspection | EDWIN GREGORYONA |
| Insulation | 2/27/2026 | Partial Approval | JOHN KITCKO |
| Pre-Inspection | 2/27/2026 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 2/27/2026 | Partial Inspection | JOHN KITCKO |
| Deputy Wood Construction | 3/5/2026 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 4/29/2026 | Partial Approval | EDWIN GREGORYONA |
| Pre-Inspection | 4/29/2026 | Approved | EDWIN GREGORYONA |
| Wood Frame | 5/20/2026 | Partial Approval | EDWIN GREGORYONA |