15711 W ROSCOE BLVD 91343

Certificate Information: 15711 W ROSCOE BLVD 91343

Application / Permit
24016-20000-39082
Plan Check / Job No.
B24VN25385
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
E-plan. Tenant improvement of existing hotel for interim supportive housing. Including new office space, laundry room and break breakroom. Project Homekey.
Permit Issued
Issued on 3/13/2025
Issuing Office
Current Status
Issued on 3/13/2025

Permit Application Status History

Submitted 12/13/2024 APPLICANT
Assigned to Plan Check Engineer 12/19/2024 SALVADOR QUINTANILLA
Assigned to Zoning Architect 12/19/2024 LY CHEA
Corrections Issued 12/21/2024 SALVADOR QUINTANILLA
Quality Review Completed 12/23/2024 PETER KIM
Applicant returned to address corrections 1/13/2025 SALVADOR QUINTANILLA
Applicant returned to address corrections 1/14/2025 SALVADOR QUINTANILLA
Applicant returned to address corrections 1/17/2025 SALVADOR QUINTANILLA
Applicant returned to address corrections 1/31/2025 SALVADOR QUINTANILLA
Applicant returned to address corrections 3/6/2025 SALVADOR QUINTANILLA
Plan Check Approved 3/11/2025 SALVADOR QUINTANILLA
Issued 3/13/2025 APPLICANT

Permit Application Clearance Information

"Q" conditions Cleared 1/8/2025 MAYELA VILLA
ZA Case Cleared 1/8/2025 MAYELA VILLA
Miscellaneous Cleared 2/4/2025 DANIEL CORONADO
DAS Clearance Cleared 3/7/2025 Cristina Salazar
Zoning Plan Check Cleared 3/10/2025 Cristina Salazar

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/25/2025 Partial Inspection DEANDRE HOFFMAN
Deputy Drilled-In Anchors 7/15/2025 Conditional Approval DEANDRE HOFFMAN
Wood Frame 7/21/2025 Partial Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 7/28/2025 Partial Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 7/28/2025 Partial Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 7/30/2025 Partial Inspection DEANDRE HOFFMAN
Special/Order Compliance 7/30/2025 Partial Inspection DEANDRE HOFFMAN
Deputy Reinf. Concrete 7/31/2025 Conditional Approval DEANDRE HOFFMAN
Wood Frame 8/8/2025 Corrections Issued DEANDRE HOFFMAN
Pre-Inspection 8/15/2025 Partial Inspection DEANDRE HOFFMAN
Insulation 9/15/2025 Partial Approval DEANDRE HOFFMAN
Wood Frame 9/15/2025 Partial Inspection DEANDRE HOFFMAN
Pre-Inspection 9/22/2025 Partial Inspection GREGORY POMISH
Wood Frame 9/22/2025 Partial Approval GREGORY POMISH
Insulation 9/26/2025 Partial Approval DEANDRE HOFFMAN
Interior/Exterior Lathing 10/10/2025 Partial Approval GREGORY POMISH
Drywall Nailing 10/21/2025 Partial Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 10/29/2025 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 10/30/2025 Partial Approval KENNETH ROBERTS
Pre-Inspection 10/30/2025 Approved KENNETH ROBERTS
Deputy Reinf. Concrete 11/3/2025 Conditional Approval KENNETH ROBERTS
Excavation/Setback/Form/Re-Bar 12/12/2025 Not Ready for Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 12/12/2025 Not Ready for Inspection DEANDRE HOFFMAN
Deputy Reinf. Concrete 12/16/2025 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/16/2025 Not Ready for Inspection JOHN KITCKO
Special/Order Compliance 12/16/2025 Not Ready for Inspection SCOTT SOBEL
Drywall Nailing 12/24/2025 Partial Approval DEANDRE HOFFMAN
Light Gage Steel Frame 1/23/2026 Approved DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2026 Partial Approval EDWIN GREGORYONA
Wood Frame 2/11/2026 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/12/2026 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 2/20/2026 Partial Approval EDWIN GREGORYONA
Insulation 2/26/2026 Partial Inspection EDWIN GREGORYONA
Wood Frame 2/26/2026 Partial Inspection EDWIN GREGORYONA
Insulation 2/27/2026 Partial Approval JOHN KITCKO
Pre-Inspection 2/27/2026 Not Ready for Inspection JOHN KITCKO
Wood Frame 2/27/2026 Partial Inspection JOHN KITCKO
Deputy Wood Construction 3/5/2026 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 4/29/2026 Partial Approval EDWIN GREGORYONA
Pre-Inspection 4/29/2026 Approved EDWIN GREGORYONA
Wood Frame 5/20/2026 Partial Approval EDWIN GREGORYONA