408 N BEACHWOOD DR 90004
Certificate Information: 408 N BEACHWOOD DR 90004
- Application / Permit
- 24016-20000-38987
- Plan Check / Job No.
- B24VN25329
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INT/EXT REMODEL OF SFD AND CHANGE OUT WINDOWS ALL WORK PER ENGINEERING NO CHANGE IN AREA/ SETBACKS OR HEIGHT
- Permit Issued
- Issued on 1/27/2025
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 8/25/2025
Permit Application Status History
| Submitted | 12/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2024 | JESSE ARELLANO |
| Corrections Issued | 12/21/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 12/24/2024 | APPLICANT |
| Applicant returned to address corrections | 1/23/2025 | SEWADA ZADOORIAN MILAGARDI |
| Issued | 1/27/2025 | APPLICANT |
| Permit Finaled | 8/22/2025 | JEFFREY MEAD |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: C53256 | 11607 AMESTOY AVE GRANADA HILLS, CA 91344 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/5/2025 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 2/6/2025 | Conditional Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 3/17/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 3/17/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 3/18/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 3/25/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 3/25/2025 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 3/25/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 3/25/2025 | Approved | JEFFREY MEAD |
| Shower Pan | 3/25/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/8/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Rough | 4/8/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 4/8/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 4/10/2025 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2025 | Approved | JEFFREY MEAD |
| Insulation | 4/16/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 5/2/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | JEFFREY MEAD |
| Final | 8/15/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 8/15/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 8/15/2025 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 8/15/2025 | Approved | JEFFREY MEAD |
| Final | 8/22/2025 | Permit Finaled | JEFFREY MEAD |