21800 W VENTURA BLVD 91364
Certificate Information: 21800 W VENTURA BLVD 91364
- Application / Permit
- 24016-20000-38886
- Plan Check / Job No.
- B24VN25215
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Gymnasium
- Work Description
- EXTERIOR AND INTERIOR REMODEL TO EXISTING RETAIL NO ADDITIONS OR CHANGE IN BUILDING FOOTPRINT
- Permit Issued
- Issued on 2/28/2025
- Issuing Office
- Current Status
- Permit Finaled on 7/22/2026
Permit Application Status History
| Submitted | 12/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2024 | CARLOS MONTES |
| Corrections Issued | 12/17/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 1/9/2025 | CARLOS MONTES |
| Plan Check Approved | 2/11/2025 | CARLOS MONTES |
| Issued | 2/28/2025 | APPLICANT |
| Permit Finaled | 7/21/2026 | BRIAN KELLY |
Permit Application Clearance Information
| Address approval | Cleared | 12/26/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2024 | CARLOS AGUILERA |
| "D" conditions | Cleared | 1/6/2025 | MATHEW QUAN |
| Specific Plan | Cleared | 2/5/2025 | ABRAHAM LAMONTAGNE |
Contact Information
| Contractor | Bison Builders; Lic. No.: 1040834-B | , |
| Contractor | Hi-Quality Builders; Lic. No.: 1040834-B | , |
| Engineer | Dong,, Truong; Lic. No.: C75466 | 10692 SILVER CIRCLE GARDEN GROVE, CA 92843 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/22/2025 | Partial Inspection | BRIAN KELLY |
| Wood Frame | 7/31/2025 | Partial Inspection | BRIAN KELLY |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 8/5/2025 | Not Ready for Inspection | BRIAN KELLY |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Not Ready for Inspection | BRIAN KELLY |
| Interior/Exterior Lathing | 8/13/2025 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 8/13/2025 | Not Ready for Inspection | BRIAN KELLY |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | No Access for Inspection | BRIAN KELLY |
| Wood Frame | 8/14/2025 | No Access for Inspection | BRIAN KELLY |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Not Ready for Inspection | BRIAN KELLY |
| Interior/Exterior Lathing | 8/15/2025 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 8/15/2025 | Not Ready for Inspection | BRIAN KELLY |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Approved | GREGORY POMISH |
| Interior/Exterior Lathing | 8/19/2025 | Approved | GREGORY POMISH |
| Pre-Inspection | 10/28/2025 | Partial Inspection | BRIAN KELLY |
| Special/Order Compliance | 12/5/2025 | Corrections Issued | BRIAN KELLY |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Not Ready for Inspection | BRIAN KELLY |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2025 | Partial Approval | BRIAN KELLY |
| Posting Pre-Inspection | 12/26/2025 | Partial Approval | BRIAN KELLY |
| Wood Frame | 12/26/2025 | Partial Approval | BRIAN KELLY |
| Insulation | 1/22/2026 | Corrections Issued | BRIAN KELLY |
| Drywall Nailing | 2/3/2026 | Not Ready for Inspection | BRIAN KELLY |
| Drywall Nailing | 2/6/2026 | Not Ready for Inspection | BRIAN KELLY |
| Drywall Nailing | 2/10/2026 | Partial Approval | BRIAN KELLY |
| Pre-Inspection | 7/2/2026 | Not Ready for Inspection | BRIAN KELLY |
| Final | 7/15/2026 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 7/15/2026 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 7/15/2026 | Not Ready for Inspection | BRIAN KELLY |
| Final | 7/21/2026 | Permit Finaled | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 7/21/2026 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 7/21/2026 | Approved | BRIAN KELLY |