6153 N BECKFORD AVE 91335

Certificate Information: 6153 N BECKFORD AVE 91335

Application / Permit
24016-20000-38760
Plan Check / Job No.
B24VN24523
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED 20' X 20' UTILITY ROOM TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/6/2025
Issuing Office
Current Status
CofO Issued on 9/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2024 APPLICANT
Assigned to Plan Check Engineer 12/6/2024 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 12/7/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 1/30/2025 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 2/5/2025 PINANK PATEL
Issued 2/6/2025 APPLICANT
Permit Finaled 9/6/2025 MICHAEL PELHAM
CofO Issued 9/6/2025 MICHAEL PELHAM
Permit Finaled 9/6/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 12/9/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/9/2024 CARLOS AGUILERA
Sewer availability Cleared 12/9/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/11/2024 CARLOS AGUILERA
Construction near power lines Cleared 1/30/2025 GEVORK KARAPETYAN
Construction within easement Cleared 1/30/2025 GEVORK KARAPETYAN

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/3/2025 Corrections Issued SCOTT SOBEL
Footing/Foundation/Slab 3/3/2025 Corrections Issued SCOTT SOBEL
BUILDING-Rough-Frame 4/7/2025 Corrections Issued MORRIS JACKSON
Gas Test 4/7/2025 Approved MORRIS JACKSON
Green Building Rough 4/7/2025 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 4/7/2025 Not Ready for Inspection MORRIS JACKSON
Rough-Elec/Plmb/HVAC 4/7/2025 Approved MORRIS JACKSON
Sewer 4/7/2025 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 4/21/2025 Partial Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Partial Approval MORRIS JACKSON
Green Building Rough 4/21/2025 Approved MORRIS JACKSON
Insulation 4/21/2025 Approved MORRIS JACKSON
Drywall Nailing 5/15/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 5/15/2025 Approved MORRIS JACKSON
Shower Pan 5/15/2025 Approved MORRIS JACKSON
Service/Power Release 6/16/2025 Not Ready for Inspection JOHN COLEMAN
Underground Mechanical 6/16/2025 Partial Inspection JOHN COLEMAN
BUILDING-Rough-Frame 8/15/2025 Approved MORRIS JACKSON
ELECTRICAL-Final 8/15/2025 Approved MORRIS JACKSON
Final 8/15/2025 Corrections Issued MORRIS JACKSON
Green Building Final 8/15/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Not Ready MORRIS JACKSON
Service/Power Release 8/15/2025 Approved MORRIS JACKSON
Smoke Detectors 8/15/2025 Approved MORRIS JACKSON
Final 8/21/2025 Partial Approval MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV Approved MORRIS JACKSON