19928-19932 W HATTON ST 91306
Certificate Information: 19928-19932 W HATTON ST 91306
- Application / Permit
- 24016-20000-38575
- Plan Check / Job No.
- B24VN24905
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF (E) SFD TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GC 66323(a)(1) and 66333. CONVERT PORTION OF (E) SFD TO (N) ACCESSORY DWELLING UNIT per GCS 66323(a)(1) REMODEL OF SFD. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/26/2025
- Issuing Office
- Current Status
- CofO Issued on 4/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 12/13/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/16/2024 | APPLICANT |
| Applicant returned to address corrections | 1/30/2025 | MADISON ODELL |
| Issued | 2/26/2025 | APPLICANT |
| CofO in Progress | 3/17/2026 | ALEXANDER HANDY |
| Permit Finaled | 4/10/2026 | JOHN JANSON |
| CofO Issued | 4/10/2026 | JOHN JANSON |
| Permit Finaled | 4/10/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/18/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 12/18/2024 | BIAINA HARITUNIAN |
| Miscellaneous | Cleared | 12/19/2024 | ALEX VELA |
| ZA Case | Cleared | 12/19/2024 | ALEX VELA |
| ZA Case | Cleared | 12/19/2024 | ALEX VELA |
| ZA Case | Cleared | 12/19/2024 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/16/2025 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 5/16/2025 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 6/2/2025 | Corrections Issued | SCOTT SOBEL |
| Sewer | 6/2/2025 | Approved | SCOTT SOBEL |
| Deputy Drilled-In Anchors | 6/3/2025 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 6/4/2025 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 6/4/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 7/17/2025 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 7/17/2025 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 7/28/2025 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 7/28/2025 | Partial Approval | KRISTEN CAUSEY |
| Shower Pan | 7/28/2025 | Approved | KRISTEN CAUSEY |
| Insulation | 8/18/2025 | Corrections Issued | ALEXANDER HANDY |
| Interior/Exterior Lathing | 8/18/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 8/20/2025 | Approved | ALEXANDER HANDY |
| Insulation | 8/20/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 8/20/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 8/25/2025 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 9/17/2025 | Partial Approval | KRISTEN CAUSEY |
| Wood Frame | 9/17/2025 | Partial Inspection | KRISTEN CAUSEY |
| Final | 12/1/2025 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 12/1/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 12/1/2025 | Approved | ALEXANDER HANDY |
| Final | 3/9/2026 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Not Ready | ALEXANDER HANDY |
| Final | 3/12/2026 | OK to Issue CofO | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/12/2026 | SGSOV Approved | ALEXANDER HANDY |