19224 N CHASE ST 91324

Certificate Information: 19224 N CHASE ST 91324

Application / Permit
24016-20000-38528
Plan Check / Job No.
B24VN24859
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan (E) Rec room and storage room to be converted into an Accessory dwelling Unit per CA Govt. Code 65852.2(e)(1)(A). Work per WFPP.
Permit Issued
Issued on 1/2/2025
Issuing Office
Current Status
CofO Issued on 10/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2024 APPLICANT
Assigned to Plan Check Engineer 12/11/2024 NGHI SU
Corrections Issued 12/12/2024 NGHI SU
Plan Check Approved 12/23/2024 JOSEPH RAFOLS
Issued 1/2/2025 APPLICANT
CofO in Progress 9/15/2025 KRISTEN CAUSEY
Permit Finaled 10/4/2025 MICHAEL PELHAM
CofO Issued 10/4/2025 MICHAEL PELHAM
Permit Finaled 10/4/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 12/16/2024 CARLOS AGUILERA
Sewer availability Cleared 12/16/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/18/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/7/2025 No Access for Inspection DAVID SCANTLIN
Pre-Inspection 4/10/2025 Approved DAVID SCANTLIN
Pre-Inspection 4/28/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 5/12/2025 Partial Inspection KRISTEN CAUSEY
Underground Mechanical 5/12/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 5/19/2025 Approved KRISTEN CAUSEY
Green Building Rough 5/19/2025 Approved KRISTEN CAUSEY
HVAC-Rough 5/19/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 5/19/2025 Approved KRISTEN CAUSEY
Final 8/29/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 8/29/2025 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 8/29/2025 Not Ready for Inspection DAVID SCANTLIN
Final 9/12/2025 OK to Issue CofO KRISTEN CAUSEY
Green Building Final 9/12/2025 Approved KRISTEN CAUSEY
HVAC-Final 9/12/2025 Approved KRISTEN CAUSEY
PLUMBING-Final 9/12/2025 Approved KRISTEN CAUSEY
Smoke Detectors 9/12/2025 Approved KRISTEN CAUSEY