20432 W GILMORE ST 91306
Certificate Information: 20432 W GILMORE ST 91306
- Application / Permit
- 24016-20000-38141
- Plan Check / Job No.
- B24VN24538
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 111[ePlan] Convert existing detached 20'-2" x 20'-2 1/2" garage to an Accessory Dwelling Unit per state law. Work per WFPP.
- Permit Issued
- Issued on 2/4/2025
- Issuing Office
- Current Status
- CofO Issued on 3/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 12/5/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 1/29/2025 | NGHI SU |
| Plan Check Approved | 2/2/2025 | NGHI SU |
| Issued | 2/4/2025 | APPLICANT |
| CofO in Progress | 3/5/2026 | ALEXANDER HANDY |
| Permit Finaled | 3/17/2026 | JOHN JANSON |
| CofO Issued | 3/17/2026 | JOHN JANSON |
| Permit Finaled | 3/17/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/30/2024 | CARLOS AGUILERA |
| ZI | Cleared | 12/31/2024 | RUBEN VASQUEZ |
| ZI | Cleared | 12/31/2024 | RUBEN VASQUEZ |
Contact Information
| Contractor | Frontline Construction Inc; Lic. No.: 944366-B | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/29/2025 | Conditional Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 4/29/2025 | Partial Approval | ALEXANDER HANDY |
| Sewer | 4/29/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 4/29/2025 | Corrections Issued | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 5/23/2025 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 5/27/2025 | Partial Approval | ALEXANDER HANDY |
| Underground Mechanical | 5/27/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 6/9/2025 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 6/9/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 6/9/2025 | Approved | ALEXANDER HANDY |
| Insulation | 6/12/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Interior/Exterior Lathing | 6/12/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Drywall Nailing | 6/20/2025 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 6/20/2025 | Partial Approval | SCOTT SOBEL |
| Shower Pan | 6/20/2025 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 7/7/2025 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 9/19/2025 | Approved | ALEXANDER HANDY |
| Final | 9/19/2025 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 9/19/2025 | Approved | ALEXANDER HANDY |
| Final | 9/25/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/25/2025 | SGSOV Approved | ALEXANDER HANDY |
| Pre-Inspection | 2/12/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 3/4/2026 | Approved | ALEXANDER HANDY |
| Final | 3/4/2026 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 3/4/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 3/4/2026 | Approved | ALEXANDER HANDY |