19051 W CELTIC ST 91326
Certificate Information: 19051 W CELTIC ST 91326
- Application / Permit
- 24016-20000-38048
- Plan Check / Job No.
- B24VN24483
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO AND REFRAME WATER DAMAGE REPAIR TO SINGLE-FAMILY DWELLING
- Permit Issued
- Issued on 1/3/2025
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/14/2025
Permit Application Status History
| Submitted | 12/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2024 | JESSE ARELLANO |
| Corrections Issued | 12/10/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 12/13/2024 | APPLICANT |
| Plan Check Approved | 12/26/2024 | ALEC MOUSAKHANIAN |
| Issued | 1/3/2025 | APPLICANT |
| Permit Finaled | 10/10/2025 | DAVID SCANTLIN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/18/2024 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/6/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Pre-Inspection | 1/6/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 1/16/2025 | Conditional Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 1/24/2025 | Approved | DAVID SCANTLIN |
| Reinforced Concrete Frame | 1/24/2025 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 2/5/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 2/5/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 2/7/2025 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2025 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 5/5/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Final | 5/5/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Final | 5/5/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Insulation | 5/5/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Final | 5/5/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/6/2025 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 5/6/2025 | Approved | DAVID SCANTLIN |
| Green Building Rough | 5/6/2025 | Approved | DAVID SCANTLIN |
| Insulation | 5/6/2025 | Approved | DAVID SCANTLIN |
| Final | 8/21/2025 | No Access for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 8/21/2025 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 8/21/2025 | No Access for Inspection | DAVID SCANTLIN |
| Final | 10/10/2025 | Permit Finaled | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 10/10/2025 | Approved | DAVID SCANTLIN |