19051 W CELTIC ST 91326

Certificate Information: 19051 W CELTIC ST 91326

Application / Permit
24016-20000-38048
Plan Check / Job No.
B24VN24483
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO AND REFRAME WATER DAMAGE REPAIR TO SINGLE-FAMILY DWELLING
Permit Issued
Issued on 1/3/2025
Issuing Office
Valley
Current Status
Permit Finaled on 10/14/2025

Permit Application Status History

Submitted 12/2/2024 APPLICANT
Assigned to Plan Check Engineer 12/9/2024 JESSE ARELLANO
Corrections Issued 12/10/2024 JESSE ARELLANO
Building Plans Picked Up 12/13/2024 APPLICANT
Plan Check Approved 12/26/2024 ALEC MOUSAKHANIAN
Issued 1/3/2025 APPLICANT
Permit Finaled 10/10/2025 DAVID SCANTLIN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/18/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/6/2025 Not Ready for Inspection DAVID SCANTLIN
Pre-Inspection 1/6/2025 Not Ready for Inspection DAVID SCANTLIN
Deputy Drilled-In Anchors 1/16/2025 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 1/24/2025 Approved DAVID SCANTLIN
Reinforced Concrete Frame 1/24/2025 Approved DAVID SCANTLIN
ELECTRICAL-Final 2/5/2025 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 2/5/2025 Corrections Issued CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 2/7/2025 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 2/13/2025 Approved KRISTEN CAUSEY
Drywall Nailing 5/5/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Final 5/5/2025 Not Ready for Inspection DAVID SCANTLIN
HVAC-Final 5/5/2025 Not Ready for Inspection DAVID SCANTLIN
Insulation 5/5/2025 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Final 5/5/2025 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 5/6/2025 Approved DAVID SCANTLIN
Drywall Nailing 5/6/2025 Approved DAVID SCANTLIN
Green Building Rough 5/6/2025 Approved DAVID SCANTLIN
Insulation 5/6/2025 Approved DAVID SCANTLIN
Final 8/21/2025 No Access for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 8/21/2025 No Access for Inspection DAVID SCANTLIN
Final 10/10/2025 Permit Finaled DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 10/10/2025 Approved DAVID SCANTLIN