7400-7402 N RIVERTON AVE 91352

Certificate Information: 7400-7402 N RIVERTON AVE 91352

Application / Permit
24016-20000-37959
Plan Check / Job No.
B24VN24396
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22. PER WFPP.
Permit Issued
Issued on 12/12/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2024 APPLICANT
Assigned to Plan Check Engineer 12/6/2024 JEROME MAGAT PALMA
Corrections Issued 12/10/2024 JEROME MAGAT PALMA
Building Plans Picked Up 12/11/2024 APPLICANT
Issued 12/12/2024 APPLICANT
CofO in Progress 9/9/2025 JOSE AVILA
Permit Finaled 11/19/2025 RUBEN SALAS
CofO Issued 11/19/2025 RUBEN SALAS
Permit Finaled 11/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/9/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/9/2024 RYAN CASTRO
Sewer availability Cleared 12/9/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/30/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Pre-Inspection 2/3/2025 Approved ROBERTO PALACIOS-LOPEZ
Sewer 2/3/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 2/3/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/5/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Underground Mechanical 2/5/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 2/7/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/11/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 3/11/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/11/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/13/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 3/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 3/13/2025 Approved ROBERTO PALACIOS-LOPEZ
Wood Frame 3/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 3/18/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/20/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/20/2025 Conditional Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 3/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 3/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 3/24/2025 Approved JOSE AVILA
PLUMBING-Rough 4/7/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 4/21/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/22/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 8/8/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Final 8/18/2025 Approved JOSE AVILA
Green Building Final 8/18/2025 Approved JOSE AVILA
Green Building Rough 8/18/2025 Approved JOSE AVILA
HVAC-Final 8/18/2025 Approved JOSE AVILA
PLUMBING-Final 8/18/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/18/2025 SGSOV Approved JOSE AVILA
Service/Power Release 8/18/2025 Approved JOSE AVILA
Smoke Detectors 8/18/2025 Approved JOSE AVILA
Final 9/8/2025 OK to Issue CofO JOSE AVILA