22151-22153 W BALTAR ST 91304

Certificate Information: 22151-22153 W BALTAR ST 91304

Application / Permit
24016-20000-37868
Plan Check / Job No.
B24VN24369
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 3'9" X 4'10" PORTION OF (E) ATTACHED GARAGE TO LAUNDRY ROOM FOR (E) SFD AND REMAINING PORTION TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) & REMODEL (E) SFD.
Permit Issued
Issued on 12/16/2024
Issuing Office
Current Status
Issued on 12/16/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/27/2024 APPLICANT
Assigned to Plan Check Engineer 12/4/2024 ARTIN ZARUKIAN
Corrections Issued 12/7/2024 ARTIN ZARUKIAN
Building Plans Picked Up 12/11/2024 APPLICANT
Plan Check Approved 12/16/2024 OMAR GARNICA
Issued 12/16/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/12/2024 RYAN CASTRO
Sewer availability Cleared 12/12/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/13/2024 RYAN CASTRO

Contact Information

Contractor Ivy Green Construction; Lic. No.: 1014647-B 14537 VENTURA BLVD      SHERMAN OAKS, CA 91403
Engineer Valencia,, Byron Steve; Lic. No.: C87372 16000 VENTURA BLVD., PH 1203      ENCINO, CA 91436

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2025 Partial Approval JEFFREY HARTLINE
Deputy Drilled-In Anchors 2/20/2025 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 2/24/2025 Partial Approval DAVID SCANTLIN
Wood Frame 2/24/2025 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 3/7/2025 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Rough 3/7/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 3/7/2025 Partial Approval JEFFREY HARTLINE
Shower Pan 3/7/2025 Partial Approval JEFFREY HARTLINE
Insulation 3/12/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/12/2025 Partial Approval CHRIS CHRISTENSEN
Insulation 3/18/2025 Approved JEFFREY HARTLINE
Drywall Nailing 3/20/2025 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 3/27/2025 Partial Approval JEFFREY HARTLINE