20225 W ALLENTOWN DR 91364
Certificate Information: 20225 W ALLENTOWN DR 91364
- Application / Permit
- 24016-20000-37697
- Plan Check / Job No.
- B24VN24255
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: INTERIOR REMODEL TO (E) SFD, REMOVE TWO LOAD BEARING WALLS, ADD A BATHROOM AT SECOND FLOOR, POWDER ROOM AT FIRST FLOOR, AND REMODEL KITCHEN. ALL WORK PER ENG.
- Permit Issued
- Issued on 12/12/2024
- Issuing Office
- Current Status
- Permit Finaled on 4/21/2025
Permit Application Status History
| Submitted | 11/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 12/3/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 12/12/2024 | ISIS ARGUETA |
| Issued | 12/12/2024 | APPLICANT |
| Permit Finaled | 4/21/2025 | JOHN HAYES |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/5/2024 | CHARLES POWELL |
Contact Information
| Contractor | 4 Angels Tabe Inc; Lic. No.: 987871-B | , |
| Contractor | New Look Surface; Lic. No.: 987871-B | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/19/2024 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 12/20/2024 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 12/20/2024 | Corrections Issued | JOHN COLEMAN |
| Shower Pan | 12/20/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 12/24/2024 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 12/24/2024 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 12/24/2024 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 12/24/2024 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 12/31/2024 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 1/3/2025 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 1/3/2025 | Approved | MORRIS JACKSON |
| Insulation | 1/3/2025 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 1/3/2025 | Partial Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/7/2025 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Rough | 1/7/2025 | Approved | JOHN COLEMAN |
| Drywall Nailing | 1/16/2025 | Approved | JOHN HAYES |
| Final | 4/21/2025 | Permit Finaled | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 4/21/2025 | Approved | JOHN HAYES |