11828 W HARTSOOK ST 91607

Certificate Information: 11828 W HARTSOOK ST 91607

Application / Permit
24016-20000-37639
Plan Check / Job No.
B24VN24185
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE/STORAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). REMOVE PORTION OF (E) STORAGE.
Permit Issued
Issued on 1/16/2025
Issuing Office
Metro
Current Status
CofO Issued on 5/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2024 APPLICANT
Assigned to Plan Check Engineer 12/3/2024 ISIS ARGUETA
Corrections Issued 12/3/2024 ISIS ARGUETA
Building Plans Picked Up 12/5/2024 APPLICANT
Applicant returned to address corrections 12/18/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 1/14/2025 ISIS ARGUETA
Issued 1/16/2025 APPLICANT
CofO in Progress 6/10/2025 JAVIER RAMOS JR
CofO Issued 5/21/2026 RUBEN SALAS
Permit Finaled 5/21/2026 RUBEN SALAS

Permit Application Clearance Information

Specific Plan Cleared 12/6/2024 JOANNA MARROQUIN
Address approval Cleared 12/9/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/9/2024 RYAN CASTRO
Sewer availability Cleared 12/9/2024 RYAN CASTRO

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Edmundo Santiago Merida; Lic. No.: 1125094-B 4435 TOPAZ ST      LOS ANGELES, CA 90032

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/7/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 2/7/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/7/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 3/7/2025 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 3/7/2025 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/14/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/4/2025 Approved JAVIER RAMOS JR
HVAC-Rough 4/4/2025 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 4/4/2025 Approved JAVIER RAMOS JR
Sewer 4/4/2025 Approved JAVIER RAMOS JR
Underground Mechanical 4/4/2025 Approved JAVIER RAMOS JR
HVAC-Rough 4/17/2025 Approved JAVIER RAMOS JR
Insulation 4/17/2025 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 4/17/2025 Partial Approval JAVIER RAMOS JR
Shower Pan 4/17/2025 Approved JAVIER RAMOS JR
Drywall Nailing 4/25/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 4/25/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 6/3/2025 Approved JAVIER RAMOS JR
Final 6/3/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 6/3/2025 Approved JAVIER RAMOS JR
Insulation 6/3/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 6/3/2025 Approved JAVIER RAMOS JR
Smoke Detectors 6/3/2025 Approved JAVIER RAMOS JR
Final 6/10/2025 OK to Issue CofO JAVIER RAMOS JR
HVAC-Final 6/10/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 6/10/2025 Approved JAVIER RAMOS JR