22304-22306 W MARLIN PL 91303

Certificate Information: 22304-22306 W MARLIN PL 91303

Application / Permit
24016-20000-37493
Plan Check / Job No.
B24VN24050
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Attached Garage Conversion to ADU per GCS 65852.2(e)(1)(C) in (E) 1-Story SFD
Permit Issued
Issued on 12/14/2024
Issuing Office
Current Status
CofO Issued on 5/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2024 APPLICANT
Assigned to Plan Check Engineer 12/2/2024 DAVID CASTILLO
Corrections Issued 12/3/2024 DAVID CASTILLO
Plan Check Approved 12/13/2024 DAVID CASTILLO
Issued 12/14/2024 APPLICANT
CofO in Progress 5/22/2025 GEVORK IPCHYAN
Permit Finaled 5/30/2025 JOHN JANSON
CofO Issued 5/30/2025 JOHN JANSON
Permit Finaled 5/30/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/4/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/4/2024 LEE GUILBEAUX
Sewer availability Cleared 12/4/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/4/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/5/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/10/2025 Conditional Approval GEVORK IPCHYAN
Excavation/Setback/Form/Re-Bar 1/10/2025 Corrections Issued GEVORK IPCHYAN
Footing/Foundation/Slab 1/10/2025 Not Ready for Inspection GEVORK IPCHYAN
Excavation/Setback/Form/Re-Bar 1/15/2025 Approved GEVORK IPCHYAN
Underground Mechanical 1/15/2025 Approved GEVORK IPCHYAN
Deputy Drilled-In Anchors 2/6/2025 Conditional Approval TROY SANDERS
BUILDING-Rough-Frame 2/26/2025 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 2/26/2025 Approved GEVORK IPCHYAN
HVAC-Rough 2/26/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 2/26/2025 Approved GEVORK IPCHYAN
Insulation 3/6/2025 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Partial Approval GEVORK IPCHYAN
Interior/Exterior Lathing 3/11/2025 Partial Approval GEVORK IPCHYAN
Drywall Nailing 3/18/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 3/24/2025 Partial Approval GEVORK IPCHYAN
Shower Pan 3/24/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 5/15/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Final 5/15/2025 Not Ready for Inspection GEVORK IPCHYAN
Final 5/15/2025 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Final 5/15/2025 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Final 5/15/2025 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 5/15/2025 SGSOV Not Ready GEVORK IPCHYAN
Smoke Detectors 5/15/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Final 5/21/2025 Approved GEVORK IPCHYAN
Final 5/21/2025 OK to Issue CofO GEVORK IPCHYAN
HVAC-Final 5/21/2025 Approved GEVORK IPCHYAN
PLUMBING-Final 5/21/2025 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved GEVORK IPCHYAN