22304-22306 W MARLIN PL 91303
Certificate Information: 22304-22306 W MARLIN PL 91303
- Application / Permit
- 24016-20000-37493
- Plan Check / Job No.
- B24VN24050
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: Attached Garage Conversion to ADU per GCS 65852.2(e)(1)(C) in (E) 1-Story SFD
- Permit Issued
- Issued on 12/14/2024
- Issuing Office
- Current Status
- CofO Issued on 5/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2024 | DAVID CASTILLO |
| Corrections Issued | 12/3/2024 | DAVID CASTILLO |
| Plan Check Approved | 12/13/2024 | DAVID CASTILLO |
| Issued | 12/14/2024 | APPLICANT |
| CofO in Progress | 5/22/2025 | GEVORK IPCHYAN |
| Permit Finaled | 5/30/2025 | JOHN JANSON |
| CofO Issued | 5/30/2025 | JOHN JANSON |
| Permit Finaled | 5/30/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 12/4/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/4/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/4/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/10/2025 | Conditional Approval | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 1/10/2025 | Corrections Issued | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 1/10/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 1/15/2025 | Approved | GEVORK IPCHYAN |
| Underground Mechanical | 1/15/2025 | Approved | GEVORK IPCHYAN |
| Deputy Drilled-In Anchors | 2/6/2025 | Conditional Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 2/26/2025 | Partial Approval | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 2/26/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 2/26/2025 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 2/26/2025 | Approved | GEVORK IPCHYAN |
| Insulation | 3/6/2025 | Approved | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2025 | Partial Approval | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 3/11/2025 | Partial Approval | GEVORK IPCHYAN |
| Drywall Nailing | 3/18/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 3/24/2025 | Partial Approval | GEVORK IPCHYAN |
| Shower Pan | 3/24/2025 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 5/15/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 5/15/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 5/15/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| HVAC-Final | 5/15/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Final | 5/15/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/15/2025 | SGSOV Not Ready | GEVORK IPCHYAN |
| Smoke Detectors | 5/15/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 5/21/2025 | Approved | GEVORK IPCHYAN |
| Final | 5/21/2025 | OK to Issue CofO | GEVORK IPCHYAN |
| HVAC-Final | 5/21/2025 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 5/21/2025 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/21/2025 | SGSOV Approved | GEVORK IPCHYAN |