925-925 1/2 N ISABEL ST 90065
Certificate Information: 925-925 1/2 N ISABEL ST 90065
- Application / Permit
- 24016-20000-37404
- Plan Check / Job No.
- B24VN23966
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- CONVERT (E) ATTACHED GARAGE TO (N) ATTACHED JUNIOR ACCESSORY DWELLING UNIT PER GCS 66323(a)(1) AND 66333
- Permit Issued
- Issued on 7/15/2025
- Issuing Office
- Current Status
- CofO Issued on 1/29/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 11/30/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 12/9/2024 | APPLICANT |
| Applicant returned to address corrections | 3/6/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 7/3/2025 | ANGELICA DAVE |
| Plan Check Approved | 7/15/2025 | YAQUB MIRZA |
| Issued | 7/15/2025 | APPLICANT |
| CofO in Progress | 1/29/2026 | ALIZAH MAYAGOITIA |
| Permit Finaled | 1/29/2026 | DEROLD HAUFF |
| CofO Issued | 1/29/2026 | DEROLD HAUFF |
| Permit Finaled | 1/29/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/12/2025 | CHRISTINA BRACO |
| Address approval | Cleared | 3/18/2025 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2025 | CHRISTINA BRACO |
| Grading Pre-Inspection | Cleared | 3/20/2025 | MICHAEL TEMPLE |
| Specific Plan | Cleared | 3/24/2025 | PABLO ESTRADA |
Contact Information
| Contractor | Lloveras Carlos J; Lic. No.: 1082043-B | 965 SERFAS CLUB DRIVE CORONA, CA 92882 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/21/2025 | Approved | ALIZAH MAYAGOITIA |
| Sewer | 7/21/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/23/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/11/2025 | Partial Approval | GEM DE OCAMPO |
| ELECTRICAL-Rough | 10/1/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 10/1/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/1/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/8/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/17/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 10/17/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/17/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 10/20/2025 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 10/28/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 12/23/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 12/23/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 12/23/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 12/23/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 12/23/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 12/23/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 12/23/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV No Gas | ALIZAH MAYAGOITIA |
| Smoke Detectors | 12/23/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 1/9/2026 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Final | 1/12/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 1/28/2026 | OK to Issue CofO | ALIZAH MAYAGOITIA |