7903 S DENROCK AVE 90045
Certificate Information: 7903 S DENROCK AVE 90045
- Application / Permit
- 24016-20000-37304
- Plan Check / Job No.
- B24VN23903
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
- Permit Issued
- Issued on 2/11/2025
- Issuing Office
- Current Status
- CofO Issued on 8/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 11/28/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/3/2024 | APPLICANT |
| Plan Check Approved | 2/11/2025 | GIOVANNY CHAVEZ |
| Issued | 2/11/2025 | APPLICANT |
| CofO in Progress | 8/13/2025 | JESUS PINEDA |
| Permit Finaled | 8/19/2025 | RICHARD STEINBACH |
| CofO Issued | 8/19/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/19/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/13/2024 | VASIL MIHALEV |
| Specific Plan | Cleared | 12/16/2024 | HAMID GHAEMMAGHAMI |
| Address approval | Cleared | 12/17/2024 | DIANA RENTERIA |
| Sewer availability | Cleared | 12/17/2024 | DIANA RENTERIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2025 | LIAM ODONOVAN |
| Construction near power lines | Cleared | 2/7/2025 | ENRIQUE ACOSTA |
| Construction within easement | Cleared | 2/7/2025 | ENRIQUE ACOSTA |
Contact Information
| Contractor | Remodelme Inc; Lic. No.: 1066731-B | 14930 VENTURA BLVD #100 SHERMAN OAKS, CA 91403 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/28/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 4/28/2025 | Partial Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 5/19/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2025 | Partial Approval | JESUS PINEDA |
| HVAC-Rough | 5/19/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 5/19/2025 | Approved | JESUS PINEDA |
| Sewer | 5/19/2025 | Partial Approval | JESUS PINEDA |
| Underground Mechanical | 5/19/2025 | Corrections Issued | JESUS PINEDA |
| Sewer | 6/3/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 6/17/2025 | Approved | BOBBY KEY |
| Final | 6/17/2025 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 6/17/2025 | Approved | BOBBY KEY |
| Insulation | 6/17/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 6/17/2025 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 6/17/2025 | Corrections Issued | BOBBY KEY |
| Drywall Nailing | 6/25/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 6/25/2025 | Approved | JAYLIN GRAVITTE |
| Special/Order Compliance | 6/25/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 7/3/2025 | Approved | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 8/7/2025 | Corrections Issued | JESUS PINEDA |
| Final | 8/7/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 8/7/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 8/7/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/7/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/7/2025 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 8/7/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 8/12/2025 | Approved | JESUS PINEDA |
| Final | 8/12/2025 | OK to Issue CofO | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/12/2025 | SGSOV Approved | JESUS PINEDA |