12957 W CHIPPEWA ST 91342

Certificate Information: 12957 W CHIPPEWA ST 91342

Application / Permit
24016-20000-37208
Plan Check / Job No.
B24VN23784
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d).
Permit Issued
Issued on 12/6/2024
Issuing Office
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 HAYATO TSUCHIYA
Corrections Issued 11/30/2024 HAYATO TSUCHIYA
Building Plans Picked Up 12/5/2024 APPLICANT
Plan Check Approved 12/6/2024 MIROOSH KHACHATOORIAN
Issued 12/6/2024 APPLICANT
CofO in Progress 9/25/2025 KEVIN BERBERYAN
CofO Issued 10/14/2025 RUBEN SALAS
Permit Finaled 10/14/2025 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/4/2024 CHARLES POWELL
Address approval Cleared 12/5/2024 EDGAR ALCARAZ
Sewer availability Cleared 12/5/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/6/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/13/2024 Conditional Approval KEVIN BERBERYAN
Footing/Foundation/Slab 12/20/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 12/20/2024 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 2/4/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 2/4/2025 Approved KEVIN BERBERYAN
Green Building Rough 2/4/2025 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Rough 2/4/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 2/4/2025 Approved KEVIN BERBERYAN
Insulation 2/25/2025 Approved KEVIN BERBERYAN
Drywall Nailing 3/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 3/27/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 4/15/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 4/21/2025 Approved KEVIN BERBERYAN
Sewer 5/5/2025 Approved KEVIN BERBERYAN
Final 7/23/2025 No Access for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Not Ready KEVIN BERBERYAN
PLUMBING-Final 7/24/2025 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 7/29/2025 Approved KEVIN BERBERYAN
Final 7/29/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Final 7/29/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 7/29/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 7/29/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 9/22/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 9/22/2025 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/22/2025 SGSOV No Gas KEVIN BERBERYAN
Smoke Detectors 9/22/2025 Approved KEVIN BERBERYAN
Final 9/25/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 9/25/2025 Approved KEVIN BERBERYAN