12957 W CHIPPEWA ST 91342
Certificate Information: 12957 W CHIPPEWA ST 91342
- Application / Permit
- 24016-20000-37208
- Plan Check / Job No.
- B24VN23784
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d).
- Permit Issued
- Issued on 12/6/2024
- Issuing Office
- Current Status
- CofO Issued on 10/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 11/30/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 12/5/2024 | APPLICANT |
| Plan Check Approved | 12/6/2024 | MIROOSH KHACHATOORIAN |
| Issued | 12/6/2024 | APPLICANT |
| CofO in Progress | 9/25/2025 | KEVIN BERBERYAN |
| CofO Issued | 10/14/2025 | RUBEN SALAS |
| Permit Finaled | 10/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/4/2024 | CHARLES POWELL |
| Address approval | Cleared | 12/5/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/5/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/13/2024 | Conditional Approval | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 12/20/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/20/2024 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Partial Approval | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 2/4/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 2/4/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 2/4/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 2/4/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 2/4/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 2/25/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 3/10/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 3/27/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/15/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/21/2025 | Approved | KEVIN BERBERYAN |
| Sewer | 5/5/2025 | Approved | KEVIN BERBERYAN |
| Final | 7/23/2025 | No Access for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Not Ready | KEVIN BERBERYAN |
| PLUMBING-Final | 7/24/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 7/29/2025 | Approved | KEVIN BERBERYAN |
| Final | 7/29/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Final | 7/29/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 7/29/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 7/29/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 9/22/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/22/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2025 | SGSOV No Gas | KEVIN BERBERYAN |
| Smoke Detectors | 9/22/2025 | Approved | KEVIN BERBERYAN |
| Final | 9/25/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 9/25/2025 | Approved | KEVIN BERBERYAN |