1546 1/2 W 45TH ST 90062

Certificate Information: 1546 1/2 W 45TH ST 90062

Application / Permit
24016-20000-37065
Plan Check / Job No.
B24VN23614
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET GARAGE TO ADU PER CA Govt.Code 65852.2(e)(1)(A)
Permit Issued
Issued on 12/24/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2024 APPLICANT
Assigned to Plan Check Engineer 11/27/2024 SERGIO MUNIZ
Corrections Issued 11/27/2024 SERGIO MUNIZ
Building Plans Picked Up 12/3/2024 APPLICANT
Plan Check Approved 12/13/2024 YAQUB MIRZA
Issued 12/24/2024 APPLICANT
CofO in Progress 3/13/2025 SABAS ALONSO
Permit Finaled 3/13/2025 DEROLD HAUFF
CofO Issued 3/13/2025 DEROLD HAUFF
Permit Finaled 3/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/6/2024 ABEL CASILLAS
Sewer availability Cleared 12/6/2024 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 12/14/2024 ABEL CASILLAS

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 12/26/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 12/26/2024 Approved SABAS ALONSO
HVAC-Rough 12/26/2024 Approved SABAS ALONSO
PLUMBING-Rough 12/26/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/30/2024 Approved SABAS ALONSO
Green Building Rough 12/30/2024 Approved SABAS ALONSO
Drywall Nailing 12/31/2024 Approved SABAS ALONSO
Gas Test 1/7/2025 Approved SABAS ALONSO
Green Building Final 1/14/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 1/14/2025 SGSOV Approved SABAS ALONSO
Smoke Detectors 1/14/2025 Approved SABAS ALONSO
Final 1/15/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 3/4/2025 Approved SABAS ALONSO
HVAC-Final 3/4/2025 Approved SABAS ALONSO
Final 3/12/2025 OK to Issue CofO SABAS ALONSO