7930-7932 N FULTON AVE 91605

Certificate Information: 7930-7932 N FULTON AVE 91605

Application / Permit
24016-20000-36673
Plan Check / Job No.
B24VN23279
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX ATTACHED GARAGE INTO JR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) & 65852.22. PROPOSED INT REMODEL TO DEMO WALL BETWEEN BEDRM/HALLWAY/LIVING RM TO CONVERT BEDRM INTO DINING 'AREA'. AND CLOSET REMODEL PER PLAN.
Permit Issued
Issued on 12/11/2024
Issuing Office
Current Status
CofO Issued on 8/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2024 APPLICANT
Assigned to Plan Check Engineer 11/22/2024 HAYATO TSUCHIYA
Corrections Issued 11/23/2024 HAYATO TSUCHIYA
Building Plans Picked Up 11/26/2024 APPLICANT
Plan Check Approved 12/11/2024 SERGIO MUNIZ
Issued 12/11/2024 APPLICANT
CofO in Progress 7/10/2025 VINCENT HANLEY
Permit Finaled 8/4/2025 RUBEN SALAS
CofO Issued 8/4/2025 RUBEN SALAS
Permit Finaled 8/4/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/2/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/2/2024 CARLOS AGUILERA
Sewer availability Cleared 12/2/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/26/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 4/2/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/2/2025 Approved VINCENT HANLEY
PLUMBING-Rough 4/3/2025 Partial Approval VINCENT HANLEY
Sewer 4/3/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/25/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/25/2025 Approved VINCENT HANLEY
Green Building Rough 4/25/2025 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 4/25/2025 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 5/1/2025 Partial Approval VINCENT HANLEY
PLUMBING-Rough 5/1/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 5/16/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 5/16/2025 Approved VINCENT HANLEY
Green Building Rough 5/16/2025 Approved VINCENT HANLEY
HVAC-Rough 5/16/2025 Approved VINCENT HANLEY
PLUMBING-Rough 5/16/2025 Approved VINCENT HANLEY
Insulation 5/20/2025 Approved RYAN SALAZAR
Drywall Nailing 5/23/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/23/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 6/24/2025 Approved VINCENT HANLEY
Final 6/24/2025 Partial Approval VINCENT HANLEY
Green Building Final 6/24/2025 Approved VINCENT HANLEY
HVAC-Final 6/24/2025 Approved VINCENT HANLEY
PLUMBING-Final 6/24/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/24/2025 SGSOV Approved VINCENT HANLEY
Smoke Detectors 6/24/2025 Approved VINCENT HANLEY
Final 7/9/2025 OK to Issue CofO VINCENT HANLEY