6691 N BIRCHTON AVE 91307
Certificate Information: 6691 N BIRCHTON AVE 91307
- Application / Permit
- 24016-20000-36657
- Plan Check / Job No.
- B24VN23265
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Addition at front, rear deck extension and remodel of two story single family dwelling with minor structural alterations.
- Permit Issued
- Issued on 12/13/2024
- Issuing Office
- Current Status
- CofO Issued on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2024 | ALEXANDER JOO |
| Corrections Issued | 11/21/2024 | ALEXANDER JOO |
| Plan Check Approved | 12/12/2024 | JOSEPH RAFOLS |
| Issued | 12/13/2024 | APPLICANT |
| CofO in Progress | 4/22/2025 | GEVORK IPCHYAN |
| Permit Finaled | 5/7/2025 | JOHN JANSON |
| CofO Issued | 5/7/2025 | JOHN JANSON |
| Permit Finaled | 5/7/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/27/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2024 | EDGAR ALCARAZ |
Contact Information
| Architect | Ibe,, Romano Mercado; Lic. No.: NA40726 | , |
| Contractor | Owner-Builder | , |
| Engineer | Lao,, Arturo Begino; Lic. No.: NA56687 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/24/2024 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 12/30/2024 | Approved | TROY SANDERS |
| PLUMBING-Rough | 1/9/2025 | Approved | TROY SANDERS |
| Insulation | 1/14/2025 | Approved | TROY SANDERS |
| Structural Steel Frame | 1/22/2025 | Approved | TROY SANDERS |
| Drywall Nailing | 1/29/2025 | Approved | TROY SANDERS |
| Drywall Nailing | 3/26/2025 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 4/17/2025 | Approved | GEVORK IPCHYAN |
| Final | 4/17/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 4/17/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Rough | 4/17/2025 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 4/17/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 4/21/2025 | Approved | GEVORK IPCHYAN |
| Final | 4/21/2025 | OK to Issue CofO | GEVORK IPCHYAN |
| Green Building Final | 4/21/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 4/21/2025 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 4/21/2025 | Approved | GEVORK IPCHYAN |