4603 N STARK AVE 91364

Certificate Information: 4603 N STARK AVE 91364

Application / Permit
24016-20000-36642
Plan Check / Job No.
B24VN23244
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT A 152 SQ. FT. PORTION OF THE THREE CAR GARAGE INTO A (N) BEDROOM AND BATHROOM. REMOVE (E) PATIO COVER (384 S.F).
Permit Issued
Issued on 11/22/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2024 APPLICANT
Assigned to Plan Check Engineer 11/15/2024 DANIEL ABRAMYAN
Corrections Issued 11/15/2024 DANIEL ABRAMYAN
Plan Check Approved 11/22/2024 GIOVANNY CHAVEZ
Issued 11/22/2024 APPLICANT
CofO in Progress 4/24/2025 JOHN HAYES
Permit Finaled 4/29/2025 JOHN JANSON
CofO Issued 4/29/2025 JOHN JANSON
Permit Finaled 4/29/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/19/2024 BIAINA HARITUNIAN
Sewer availability Cleared 11/19/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/10/2024 Partial Approval JOHN HAYES
ELECTRICAL-Rough 1/3/2025 Approved SEAN WIRCH
Footing/Foundation/Slab 1/3/2025 Corrections Issued SEAN WIRCH
HVAC-Rough 1/3/2025 Approved SEAN WIRCH
PLUMBING-Rough 1/3/2025 Approved SEAN WIRCH
BUILDING-Rough-Frame 2/4/2025 Partial Approval JOHN HAYES
Green Building Rough 2/4/2025 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 2/4/2025 Partial Approval JOHN HAYES
Insulation 2/20/2025 Approved JOHN COLEMAN
Interior/Exterior Lathing 2/20/2025 Partial Approval JOHN COLEMAN
Drywall Nailing 2/26/2025 Approved JOHN HAYES
Interior/Exterior Lathing 2/26/2025 Approved JOHN HAYES
BUILDING-Rough-Frame 3/17/2025 Approved JOHN COLEMAN
ELECTRICAL-Final 3/17/2025 Approved JOHN COLEMAN
Final 3/17/2025 Partial Inspection JOHN COLEMAN
Green Building Final 3/17/2025 Partial Inspection JOHN COLEMAN
PLUMBING-Final 3/17/2025 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 3/17/2025 SGSOV Approved JOHN COLEMAN
Smoke Detectors 3/17/2025 Approved JOHN COLEMAN
Green Building Final 3/18/2025 Corrections Issued JOHN COLEMAN
Final 4/23/2025 OK to Issue CofO JOHN HAYES
Green Building Final 4/23/2025 Approved JOHN HAYES