5125 E CAVANAGH ROAD 90032
Certificate Information: 5125 E CAVANAGH ROAD 90032
- Application / Permit
- 24016-20000-36619
- Plan Check / Job No.
- B24VN23223
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 1ST FLOOR STORAGE ROOM TO ACCESSORY DWELLING UNIT (256 SQ FT) PER LAMC 12.22 A.33(c) and (d). "COMPLY WITH DEPARTMENT ORDER effective date 05/11/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 11/23/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 11/26/2024 | APPLICANT |
| Applicant returned to address corrections | 1/16/2025 | HAYATO TSUCHIYA |
| Plan Check Approved | 1/17/2025 | SARKIS HARABEDIAN |
| Issued | 1/17/2025 | APPLICANT |
| CofO in Progress | 4/4/2025 | DANIEL DELACRUZ |
| Permit Finaled | 7/1/2025 | DANIEL SANCHEZ |
| CofO Issued | 7/1/2025 | DANIEL SANCHEZ |
| Permit Finaled | 7/1/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 12/10/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2024 | DAVID LOPEZ |
| "D" conditions | Cleared | 12/30/2024 | ROSALINDA MEZA |
| "Q" conditions | Cleared | 12/30/2024 | ROSALINDA MEZA |
| ZI | Cleared | 12/31/2024 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/29/2025 | Partial Inspection | DANIEL DELACRUZ |
| Footing/Foundation/Slab | 2/4/2025 | Partial Inspection | DANIEL DELACRUZ |
| Underground Mechanical | 2/4/2025 | Partial Inspection | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 2/10/2025 | Partial Approval | DANIEL DELACRUZ |
| PLUMBING-Rough | 2/10/2025 | Partial Approval | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 2/19/2025 | Approved | DANIEL DELACRUZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Approved | DANIEL DELACRUZ |
| Interior/Exterior Lathing | 2/19/2025 | Approved | DANIEL DELACRUZ |
| PLUMBING-Rough | 2/19/2025 | Approved | DANIEL DELACRUZ |
| Insulation | 2/25/2025 | Approved | PEDRO SIERRA |
| Drywall Nailing | 2/28/2025 | Approved | PEDRO SIERRA |
| BUILDING-Rough-Frame | 3/24/2025 | Approved | DANIEL DELACRUZ |
| ELECTRICAL-Final | 3/24/2025 | Approved | DANIEL DELACRUZ |
| Final | 3/24/2025 | Partial Approval | DANIEL DELACRUZ |
| Green Building Final | 3/24/2025 | Approved | DANIEL DELACRUZ |
| Green Building Rough | 3/24/2025 | Approved | DANIEL DELACRUZ |
| HVAC-Final | 3/24/2025 | Approved | DANIEL DELACRUZ |
| PLUMBING-Final | 3/24/2025 | Approved | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 3/24/2025 | SGSOV Approved | DANIEL DELACRUZ |
| Smoke Detectors | 3/24/2025 | Approved | DANIEL DELACRUZ |
| Final | 4/4/2025 | OK to Issue CofO | DANIEL DELACRUZ |