12533 W CUMPSTON ST 91607
Certificate Information: 12533 W CUMPSTON ST 91607
- Application / Permit
- 24016-20000-36369
- Plan Check / Job No.
- B24VN22951
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Convert (E) patio covered into livable space. Per engineering design.
- Permit Issued
- Issued on 12/12/2024
- Issuing Office
- Current Status
- CofO Issued on 4/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2024 | APPLICANT |
| Corrections Issued | 11/17/2024 | ALFREDO JARA |
| Assigned to Plan Check Engineer | 11/18/2024 | ALFREDO JARA |
| Corrections Issued | 11/19/2024 | ALFREDO JARA |
| Plan Check Approved | 12/10/2024 | ALFREDO JARA |
| Issued | 12/12/2024 | APPLICANT |
| CofO in Progress | 1/29/2025 | OGANES TARAKHCHYAN |
| CofO in Progress | 3/19/2025 | OGANES TARAKHCHYAN |
| CofO in Progress | 3/19/2025 | OGANES TARAKHCHYAN |
| CofO Issued | 4/25/2025 | RUBEN SALAS |
| Permit Finaled | 4/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/27/2024 | JOANNA MARROQUIN |
| ZI | Cleared | 11/27/2024 | JOANNA MARROQUIN |
Contact Information
| Contractor | Reuven & Co Inc; Lic. No.: 1104411-B | , |
| Engineer | Braun,, Jason; Lic. No.: C70948 | 14390 SHAWNEE ST MOORPARK, CA 93021 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/26/2024 | Approved | OGANES TARAKHCHYAN |
| Special/Order Compliance | 1/8/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 1/10/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 1/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 1/21/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/21/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 1/23/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 1/28/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 1/28/2025 | Approved | OGANES TARAKHCHYAN |