11337 N GLENOAKS BLVD 91331
Certificate Information: 11337 N GLENOAKS BLVD 91331
- Application / Permit
- 24016-20000-36363
- Plan Check / Job No.
- B24VN22947
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/22/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2024 | JESSE ARELLANO |
| Corrections Issued | 11/22/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 11/26/2024 | APPLICANT |
| Plan Check Approved | 1/16/2025 | ALEC MOUSAKHANIAN |
| Issued | 1/22/2025 | APPLICANT |
| CofO in Progress | 8/7/2025 | MICHEL ABAJAN |
| Permit Finaled | 8/15/2025 | RUBEN SALAS |
| CofO Issued | 8/15/2025 | RUBEN SALAS |
| Permit Finaled | 8/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/25/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 1/6/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Vicsinc.Com; Lic. No.: 1002544-B | P O BOX 950931 MISSION HILLS, CA 91395 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/30/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 2/3/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/3/2025 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/6/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/6/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/6/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 2/6/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/6/2025 | Approved | MICHEL ABAJAN |
| Sewer | 2/6/2025 | Approved | MICHEL ABAJAN |
| Wood Frame | 2/6/2025 | Partial Inspection | MICHEL ABAJAN |
| Insulation | 2/10/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/10/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 2/13/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| Final | 7/18/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/18/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/18/2025 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 7/18/2025 | Approved | MICHEL ABAJAN |
| Final | 8/6/2025 | OK to Issue CofO | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/6/2025 | SGSOV Approved | MICHEL ABAJAN |