9450 N CHIVERS AVE 91352
Certificate Information: 9450 N CHIVERS AVE 91352
- Application / Permit
- 24016-20000-36316
- Plan Check / Job No.
- B24VN22912
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- (ePLAN) New (2) 5-ton, top riding bridge crane at the equipment platform. Work per engineer details. See comments.
- Permit Issued
- Issued on 2/27/2025
- Issuing Office
- Current Status
- Permit Finaled on 12/4/2025
Permit Application Status History
| Submitted | 11/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2024 | VICTOR CHEN |
| Corrections Issued | 12/3/2024 | VICTOR CHEN |
| Assigned to Zoning Architect | 12/5/2024 | MELISSA QUINONES |
| Quality Review Completed | 12/16/2024 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/29/2025 | VICTOR CHEN |
| Applicant returned to address corrections | 1/31/2025 | VICTOR CHEN |
| Applicant returned to address corrections | 2/13/2025 | VICTOR CHEN |
| Plan Check Approved | 2/26/2025 | VICTOR CHEN |
| Issued | 2/27/2025 | APPLICANT |
| Permit Finaled | 12/4/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Zoning Plan Check | Cleared | 12/17/2024 | Samuel Gonzalez |
| DAS Clearance | Cleared | 2/18/2025 | Samuel Gonzalez |
Contact Information
| Contractor | American Equipment Systems Llc; Lic. No.: 1084182-D21 | 310 EAST 4500 SOUTH SUITE 320 MURRAY, UT 84107 |
| Engineer | Herman,, Richard Robert; Lic. No.: S3255 | 20790 GUM CIRCLE YORBA LINDA, CA 92886 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/3/2025 | Corrections Issued | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/3/2025 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 3/6/2025 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 3/7/2025 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 3/7/2025 | Partial Approval | JEFFREY DURAN |
| Special/Order Compliance | 3/7/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Final | 4/10/2025 | Partial Approval | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 4/10/2025 | Approved | KENNETH ROBERTS |
| Final | 4/15/2025 | Partial Inspection | ANDREW DORSO |
| Final | 4/17/2025 | Corrections Issued | ANDREW DORSO |
| Special/Order Compliance | 10/22/2025 | Not Ready for Inspection | JEFFREY DURAN |
| Deputy Steel/Welding | 11/4/2025 | Conditional Approval | ANDREW DORSO |
| Final | 12/4/2025 | Permit Finaled | JEFFREY DURAN |